Publication: Asmara Power Distribution and Rural Electrification Project : Pre-electrification Survey Analysis
Date
2006-04-28
ISSN
Published
2006-04-28
Author(s)
O'Sullivan, Kyran
Fitzgerald, Kevin
Abstract
This report presents the findings and
recommendations of a Pre-electrification Survey done in
preparation for the Asmara Power Distribution and Rural
Electrification Project. The survey was designed to
characterize energy use in existing institutions, commercial
enterprises and households before electrification and,
thereby, set a baseline for monitoring and evaluation of the
impacts of the project going forward. The report begins with
a summary of the survey s main findings. It continues with
an introduction describing the background of the project.
Section 1 presents an estimation of electrification s
benefits using the household survey data. Section 2
discusses recommendations for ongoing monitoring and
evaluation of the project. An appendix follows.
Link to Data Set
Citation
“O'Sullivan, Kyran; Fitzgerald, Kevin. 2006. Asmara Power Distribution and Rural Electrification Project : Pre-electrification Survey Analysis. © World Bank, Washington, DC. http://hdl.handle.net/10986/12590 License: CC BY 3.0 IGO.”