40711 PUBLIC FINANCIAL MANAGEMENT IN ACEH Measuring Financial Management Performance in Aceh's Local Governments Public Financial Managment in Aceh Measuring Financial Management Performance in Aceh's Local Governments WORLD BANK OFFICE JAKARTA Jakarta Stock Exchange Building Tower II/12 th floor Jl. Jenderal Sudirman Kav. 52-53 Jakarta 12910 Tel: (+62-21) 5299-3000 Fax: (+62-21) 5299-3111 Website: www.worldbank.or.id Website: www.decentralizationindonesia.org Printed in March 2007 This report is a product of the staff of the World Bank. The findings, interpretations and conclusions expressed herein do not necessarily reflect the views of the Board of Executive Directors of the World Bank or the governments they represent. Acknowledgments This report was prepared by the World Bank in cooperation with Badan Rehabilitasi dan Rekonstruksi (BRR). The report was written by Peter Rooney (World Bank, Jakarta) and produced under the guidance of Ahya Ihsan and Enrique Blanco Armas (World Bank, Banda Aceh). The process was overseen by Wolfgang Fengler (World Bank). We would like to thank Victor Bottini (World Bank, Resident Representative, Banda Aceh) for his support and facilitation of the research and dissemination of the results. We would like to express our gratitude to BRR for all its support, particularly Tedy Jiwantara Sitepu and Sudirman Said. We would also like to thank USAID-LGSP, and Andrew Urban in particular, for all its support, for training the researchers and for organizing the first round of research. The Task Manager for the preparation of the PFM framework was Rajiv Sondhi, Senior Financial Management Specialist at the World Bank. Jessica Ludwig was instrumental in the preparation of the framework and her input on the implementation was invaluable. We are grateful for the support and input from the Ministry of Home Affairs, the Ministry of Finance, AusAID, the Asian Development Bank, the Canadian International Development Agency, GTZ, USAID and DSF. Contents LIST OF FIGURES, TABLES AND CHARTS ......................................................4 GLOSSARY OF TERMS: ACRONYMS AND ABBREVIATIONS........................5 SUMMARY ..........................................................................................................7 1. PUBLIC FINANCIAL MANAGMENT IN ACEH................................9 2. THE PFM FRAMEWORK: STRATEGIC AREAS, OUTCOMES AND INDICATORS .................................................................................10 3. THE PFM SURVEY IN ACEH.........................................................14 4. DETAILED RESULTS AND ANALYSIS ........................................20 5. KEY ISSUES ..................................................................................34 6. GOING FORWARD ........................................................................37 ANNEX 1. THE PFM FRAMEWORK: STRATEGIC AREAS AND OUTCOMES ........................................................................................................38 ANNEX 2: COMPLETE FRAMEWORK: STRATEGIC AREAS, OUTCOMES AND INDICATORS.........................................................................40 ANNEX 3: LOCAL GOVERNMENTS SURVEYED..........................................61 ANNEX 4: METHODOLOGY ...........................................................................84 ANNEX 5: RESEARCHERS AND UNIVERSITIES..........................................86 ANNEX 6: PFM OUTCOMES IN ALL 21 LOCAL GOVERNMENTS IN ACEH... ........................................................................................................87 3 List of Figures, Tables and Charts Figure 1: Structure of the PFM framework...................................................................12 Chart 1: Number of indicators in each strategic area...................................................12 Table 1: PFM framework scoring guide .......................................................................15 Chart 2: PFM scores for each of the 21 local governments and provincial government.15 Table 2: PFM scores by strategic area for Aceh regional governments .........................16 Chart 3: Comparing the best-performing and the worst-performing local governments .18 Chart 4: Comparing performance in old and recently established local governments....19 Chart 5: Average PFM scores by strategic area .............................................................17 Chart 6: Regulatory framework .......................................................................................21 Chart 7: Planning and budgeting ....................................................................................22 Chart 8: Cash management............................................................................................24 Chart 9: Procurement......................................................................................................26 Chart 10: Accounting and reporting ................................................................................27 Chart 11: Internal audit ...................................................................................................28 Chart 12: Public debt and investment.............................................................................29 Chart 13: Asset management .........................................................................................31 Chart 14: External audit and oversight............................................................................32 Glossary of Terms: Acronyms and Abbreviations APEA Aceh Public Expenditure Analysis BPK (Badan Pengawasan Keuangan) State Audit Agency BPFM (Badan Pengawasan Keuangan dan Pembangunan) Financial and Development Supervisory Board Bappeda (Badan Perencanaan Pembangunan Daerah) Regional Development Planning Agency Bawasda (Badan Pengawasan Daerah) Regional Internal Audit Agency BPKD (Badan Pemeriksa Keuangan Daerah) Regional Auditing Agency BUMD (Badan Usaha Milik Daerah) Regionally owned enterprise DAU (Dana Alokasi Umum) General allocation transfer Dana Otsus (Dana Otonomi Khusus) Special Autonomy Fund Desa Village Dinas Regional Sector Office Dispenda (Dinas Pendapatan Daerah) Regional Government Revenue Office DPRD (Dewan Perwakilan Raykat Daerah) Regional Parliaments DSF Decentralized Support Facility Inpres (Instruksi Presiden) Presidential Instruction Juknis/Juklak (Petunjuk Teknis/Petunjuk Pelaksana) Technical Guidance/Implementation Guidance Kabupaten District/Regency Kepmendagri (Keputusan Menteri Dalam Negeri) Home Office Ministerial Decree Keppres (Keputusan Presiden) Presidential Decree Kota City (urban district) KPPU (Komite Pengawas Persaingan Usaha) Committee for oversight of enterprise competition LGSP Local Government Support Program LKPJ (Laporan Keterangan Pertanggungjawaban) Budget Execution Accountability Report MoF Ministry of Finance MoHA Ministry of Home Affairs Musbangdes (Musyawarah Pembangunan Desa) Village Development Meeting PAD (Pendapatan Asli Daerah) Locally sourced revenue PDAM (Perusahaan Daerah Air Minum) Regional water authority Perda (Peraturan Daerah) Regional Regulation PFM Public financial management Qanun Islamic Regional Regulation (term only used in Aceh) Renstra (Rencana Stategis) Strategic Plan RKA-SKPD (Rencana Kerja dan Anggaran Satuan Kerja Pemerintah Daerah) Work Plan and Local Government Sectoral Budget RPJMD (Rencana Pembangunan Jangka Menengah Daerah) Regional Medium-term Development Plan Sekda (Sekretariat Daerah) Regional Scretariat SK Bupati (Surat Keputusan) Bupati Decree SKPD (Satuan Kerja Perangkat Daerah) Dinas work plan budget SKO (Surat Keputusan Otorisasi) Authorization Decree Letter SPM (Surat Perintah Membaya) Payment Order SPP (Surat Permohonan Pembayaran) Payment Request USAID United States Agency for International Development 6 Summary Capacity in financial management varies widely across local governments in Aceh. While some local governments achieve reasonable outcomes in financial management capacity, others are lagging far behind. Capacity in key aspects of financial management also varies within individual local governments. Average outcomes indicate particular weaknesses in accounting and reporting, cash management and external audit. Public financial managment (PFM) framework A Public financial managment (PFM) survey was conducted in each local government in Aceh between May and November 2006. Capacity was assessed in nine key areas of financial management: (1) regulatory framework; (2) planning and budgeting; (3) cash management; (4) procurement; (5) accounting and reporting; (6) internal audit; (7) public debt and investment; (8) asset management; and (9) external audit and oversight. Each strategic area is divided into between one to five outcomes and a list of indicators requiring a `yes/no' response is provided for each outcome. The outcomes represent a desired achievement within each strategic area and indicators are used to assess the extent to which a district government has achieved these outcomes. The PFM framework provides a snapshot of financial management capacity in individual local governments, focusing particularly on policies, procedures and regulations--the environment of financial management in local governments. Particular areas of weakness in financial management in local governments are highlighted, providing a breakdown of aspects that need to be improved. Before the PFM survey was conducted, knowledge of local governments' capacity was very limited. It is hoped that these results and the analysis that accompanies them will provide input for making a more effective assessment of financial management capacity in Aceh and its impact on the process of decentralization across the province. Results Overall, the highest scoring local government is Aceh Utara (69 percent) and the lowest is Aceh Jaya (15 percent); thus scores range from good to very poor, according to the framework's scoring guide. The average score is 41 percent. Eight local governments score between 39 and 42 percent and six local governments score below 39 percent. All but 3 local governments score poorly in at least one strategic area. Thus, more than five years after the implementation of decentralization, financial management capacity remains relatively weak in fourteen local governments in Aceh. Policy implications The results have four potential applications. First, and most importantly, the results and the accompanying analysis can assist local governments in addressing their own weaknesses in financial management. By identifying areas of weakness, local governments can themselves develop strategies to improve capacity in these areas. The first step for local governments is thus to ensure the policies, procedures and regulations are in place and subsequently to ensure that compliance is achieved and that good financial management practices become institutionalized and further developed. Without compliance and institutionalization, the efforts to raise capacity will prove ineffective. Non governmental actors can provide support to local governments to develop their capacity by providing technical assistance and capacity-building training, where necessary. The provincial government can take a leading role in developing a province-wide strategy for local governments in Aceh. Second, by highlighting key areas of capacity weakness it will be possible for agencies planning to engage local governments to account for financial management capacity and highlight particular local governments suitable for specific engagements. Third, in order to encourage a pro-active approach by local governments incentives should be provided to raise financial management capacity, for example by linking part of the dana otsus (special autonomy fund) allocation to improvements in capacity. Finally, by tracking changes in financial management capacity the Government of Indonesia can make a more accurate assessment of the impact of decentralization in Aceh. Thus, policy and regulatory issues in the decentralized context can be identified and improvements in service delivery more accurately accessed. 8 1. Public financial managment in Aceh Since 2001, Indonesia has been undergoing a fundamental transformation from centralized to decentralized government. However, up to now, the transition of power and responsibility over public resources from the center to local governments of varying capacity has been poorly understood. In particular, Aceh's special autonomy status has granted the province an even greater share of financial resources to local governments. The absence of systematic qualitative and quantitative information on how this fiscal decentralization is being managed in the districts has provided the impetus to develop a measurement framework for Indonesia's local governments. The PFM framework provides one of the four pillars of the local government measurement framework. The other pillars cover public service provision, investment climate and fiscal health. By measuring performance in these four key areas, a systematic assessment of local governments' performance can be made. For Aceh, effective financial management capacity in local governments is essential if long-term development goals are to be realized. Several factors have limited FM capacity in Aceh. First, rapid decentralization in Indonesia meant that as fiscal responsibilities were devolved and financial resources shifted to the local government level there was no concurrent increase in the capacity of local governments to manage these resources. As the role of local governments prior to decentralization was primarily to carry out the development priorities of the central government, financial management systems were not developed to cope with the devolved fiscal arrangements. Second, Aceh has experienced a significant rise in the number of local governments since 2000. Of the 21 local governments existing that exist today, 11 were formed since 2000. While this does not necessarily mean that financial management capacity will always be lower in newly formed local governments, the results of the PFM survey indicate that, on average, financial management outcomes were lower in newer local governments. Third, both the tsunami and the separatist conflict may have also adversely affected financial management outcomes. Prior to the PFM survey, there was a lack of knowledge of the capacity of local governments in Aceh and more generally across Indonesia to manage their finances. If the effectiveness of decentralization is to be assessed effectively, a key component of this is an assessment of the capacity of local governments to manage their finances. If financial management remains weak more than five years after the sweeping changes brought about by decentralization, this has far reaching implications for decentralized Aceh. More important than an aggregate assessment of financial management, the aim is to create a detailed picture of financial management capacity in individual local governments across Aceh, and more generally Indonesia, as it is now the local government level that has the most impact on people's lives. Based on this premise, the PFM framework has been created to facilitate an assessment and analysis of financial management capacity at the local level. Such knowledge will have several applications. First, the results and analysis will be disseminated to the local governments themselves. Thus, local governments will be provided with an accurate independent assessment of their own financial management 9 capacity and will be able to focus on improving key areas of weakness. Second, other government agencies, such as BRR and the provincial government, will be able to use the results both for designing interventions to increase capacity and also to better design programs accounting for particular strengths and weaknesses in financial management capacity. Likewise, donors will be able to draw on the results to design capacity-building interventions and better accommodate local government capacity in a range of programs. Third, the results and analysis can also be used to provide incentives for local governments to improve their PFM capacity. For example, if the survey were repeated annually or every two years, changes in PFM capacity could be identified. Well- performing local governments could be rewarded with additional revenue via the dana otsus (special autonomy fund) to encourage further improvements, while consistently poorly-performing administrations could be excluded from this additional revenue source. This could form part of an overall strategy to provide local governments with assistance to develop their financial management capacity. 2. The PFM framework: Strategic areas, outcomes and indicators The PFM framework was developed by the World Bank and Government of Indonesia's Ministry of Home Affairs to assess local governments' financial management capacity. The framework is divided into nine strategic areas key to effective management of public finances at the district level of government: (1) regulatory framework; (2) planning and budgeting; (3) cash management; (4) procurement; (5) accounting and reporting; (6) internal audit; (7) public debt and investment; (8) asset management; and (9) external audit and oversight. Each strategic area is divided into between one and five outcomes, and a list of indicators is provided for each outcome. The outcomes represent a desired achievement within each strategic area and indicators are used to assess the extent to which a district government has achieved these outcomes. While the framework uses some national and international PFM concepts and tools, this particular PFM framework has been designed specifically for Indonesian local governments. Hence, while minimum international standards have been drawn upon, they do not form the basis of the identified ideal outcomes, as it was considered that these standards were too high to make valid assessments of local governments in an Indonesian context. Respondents are required to answer `yes' or `no' to each of the statements provided by the indicators. Affirmative responses are added for each outcome and a score is calculated according to the percentage of `yes' responses. A percentage score is thus provided for each desired outcome representing the extent to which the local government meets the outcome. By adding all the positive responses for a strategic area, a score is arrived at that represents the capacity of the local government for that aspect of financial management. Results are obtained through interviews and focus group discussions with local government representatives at the relevant departments. These include: the local planning agency (Bappeda), the finance department, the district parliament (DPRD), the local revenue department, the local treasury office and the regional monitoring agency (see Annex 4). To ensure data accuracy `yes' responses are required to be supported 10 by either relevant documentation or/and cross-checked with additional respondents. Most results could be collected within three or four days. 11 The figure below illustrates the structure of the framework, highlighting one of the strategic areas as an example. Figure 1: Structure of the PFM framework Local Government Financial Management Capacity Strategic Area 1: 2 3 4 5 6 7 8 9 Regulatory Framework Outcome 1: A local Outcome 2: A comprehensive Outcome 3: The local regulatory framework local regulatory framework regulatory framework provides for an effective required by national legislation includes measures to law enforcement and on local financial management increase transparency and organizational structure exists public participation 12 indicators 7 indicators 6 indicators Some strategic areas have more indicators than others. For example, planning and budgeting covers 53 indicators, yet debt and public investment covers only eight. The overall score for each local government is calculated as an average of the nine strategic areas; hence, each strategic area is afforded an equal weighting Chart 1: Number of indicators in each strategic area 9 22 53 8 Regulatory framework 18 Planning & budgeting Cash management Procurement Accounting & reporting Internal audit Public debt & investment 27 44 Asset management 50 12 Limitations of this framework This measurement framework is designed to be as comprehensive as possible. However, certain shortcomings are unavoidable. The framework does not claim to be capable of measuring all that there is to measure with respect to financial management and accountability of local governments. It takes into account what is feasible and realistic to achieve in the Indonesian context. Therefore, the indicators refer to the "basics" that are not only required but also considered achievable. This has been done in order to sensitize the model to the relatively modest improvements in PFM that are likely to be realized by many Indonesian local governments, at least in the near term. The framework has been developed for ease of use. A degree of selectivity has therefore been applied in including certain outcomes, indicators and diagnostic questions and leaving others out, such that the framework can be easily applied by surveyors. Internal control environments at some of the key PFM institutions may not be fully captured in this model. Assessing internal controls can be an intricate exercise. Therefore, in key regional PFM institutions, such as accounting and local treasury offices, only some leading questions have been included that would give broad indicators of the control environments. Just as it is important to have the right procedures and policies in place, it is also important to ensure that these are actually applied in practice. This framework is inclined more towards assessing the adequacy of the policies and procedures as laid down, and relies generally on discussions between the enumerators and local government officials. Capturing practices that are not in line with the regulations, policies and procedures that govern financial management is problematic. In effect, this means that a high score for, say, internal audit does not necessarily mean that the internal audit is carried out appropriately or effectively. Rather, it simply means that the policies and procedures are in place to conduct an appropriate internal audit. It is important to note that the measurement framework has been prepared in the absence of any extensive supporting information regarding current PFM processes employed across a significant number of Indonesian local governments. This was because such information was unavailable at the time the framework was developed. In the light of experience in applying the framework across Aceh, adjustments should be made in the future to make the framework more appropriate to the Indonesian context and more focused on capturing measurable PFM outcomes. 13 3. The PFM Survey in Aceh The survey in Aceh was conducted in three stages. The first round covered five local governments: Banda Aceh, Aceh Besar, Aceh Jaya, Aceh Barat and Nagan Raya. Surveys were carried out in May to June 2006. The five locations were selected as USAID-LGSP (Local Governance Support Program) had programs in all these five tsunami affected local governments. LGSP funded this first round surveys and provided training for the researchers (a three-day workshop held in Medan in April 2006). LGSP and the World Bank coordinated the survey work and observed the survey implementation. The second round was conducted in four local governments: Aceh Utara, Aceh Timur, Pidie and Bireuen. The World Bank funded and organized this round, which was conducted in July 2006. Round three was conducted in the remaining 12 local governments plus the provincial government in November 2006. This was funded by BRR and organized by the World Bank. This report focuses on the 21 local governments. The surveys were carried out by researchers from four Indonesian universities: UNSYIAH in Banda Aceh, USU in Medan, and UNHAS in Makassar and Andalas in Padang. Several researchers were also contracted from Aceh NGOs. The researchers had strong academic backgrounds in financial management, most with a relevant MSc, and some with a PhD. Initial results have already been published in the World Bank's Aceh Public Expenditure Review1 and in BRR's Aceh and Nias Two Years after the Tsunami2. It is expected that future stages of the implementation of the PFM framework will cover the rest of Indonesia. LGSP has also surveyed several local governments outside Aceh, focusing on strategic areas relating to their capacity-building programs. PFM results in Aceh The radar below (Chart 2) highlights the divergence in financial management capacity across Aceh. The average score for all 21 local governments is 41 percent. Of immediate concern, nine local governments score under 40 percent (poor) and five local governments score between 40 and 42 percent. Only one, Aceh Utara, scores over 60 percent. It should be noted that low scores are not necessarily the result of a poorly managed incumbent civil service and/or an ineffective local government. A host of factors have led to poor outcomes in financial management, such as the whether the district is administered by an acting bupati, the quality of the staff in a remote area, the historical incidence of conflict, the immediate impact of the tsunami, a history of poorly managed previous administrations and a lack of financial resources. Current low levels of capacity in many local governments need immediate and sustained attention. Specific weaknesses highlight areas on which to focus capacity-building measures. Change over time can, and should, be attributed to the government officials responsible. Improvements should be recognized and rewarded, and failures duly noted and accounted for. 1Aceh Public Expenditure Analysis ­ Spending for Reconstruction and Poverty Reduction. World Bank, 2006. 2Aceh and Nias Two Years after the Tsunami, Badan Rehabilitasi dan Rekonstruksi, 2006. 14 Results overview The PFM scores for all 21 local governments, plus the provincial government, are listed below. A scoring guide is provided to show the grading of scores from excellent to very poor. Table 1: PFM framework scoring guide Scoring Guide 81-100% Excellent/Fully acceptable 61-80% Good/Substantially acceptable 41-60% Moderate/Partially acceptable 21-40% Poor/Substantially unacceptable 0-20% Very poor/Unacceptable Chart 2: PFM scores for each of the 21 local governments and provincial government 100 80 60 (%) score 40 20 0 Aceh Ga Pid Sab Ave A. Ace Bire A. Ace ie h Utara Banda AcehBesar Aceh yo Tamiang AcehBarat Aceh h Aceh Timur Langsa SimeulueSingkil NAD Lues ang rage Tenggara Selatanuen Tengah Nagan LhokseumA.awe Bener Raya Barat Jaya Daya Meriah 15 Table 2: PFM scores by strategic area for Aceh regional governments S T R A T E G I C A R E A Government Overall Regulatory Planning Cash Procurement Accounting Internal Public Asset External score framework & management & audit debt & management audit & budgeting reporting investment oversight 1 Aceh Utara 69 68 74 57 78 63 78 63 68 67 2 Banda Aceh 56 48 53 61 68 59 56 50 41 67 3 Aceh Besar 54 56 42 48 62 59 67 38 45 67 4 Aceh Timur 52 68 51 34 64 52 78 50 36 33 5 Langsa 50 56 55 43 66 48 61 50 36 33 6 Simeulue 49 36 51 43 76 52 56 25 50 56 7 Singkil 47 44 51 39 68 33 50 50 36 56 8 Gayo Lues 42 36 51 34 58 74 39 25 32 33 9 Pidie 42 32 36 48 72 41 67 0 50 33 10 Sabang 41 36 34 41 54 59 50 0 41 56 11 A. Tenggara 40 48 49 27 74 19 50 38 32 22 12 Aceh Selatan 40 24 49 16 58 22 44 38 50 56 13 Bireuen 39 32 47 36 72 41 44 12 36 33 14 A. Tamiang 39 44 30 39 58 37 44 38 27 33 15 Aceh Barat 39 8 26 50 70 19 61 50 64 0 16 Aceh Tengah 33 32 40 23 56 30 33 13 27 44 17 Nagan Raya 29 12 25 23 64 19 67 12 41 0 18 Lhokseumawe 29 24 33 36 32 33 50 0 18 33 19 A. Barat Daya 26 24 42 14 48 15 44 25 14 11 20 Bener Meriah 25 20 30 18 38 15 33 13 27 33 21 Aceh Jaya 15 20 25 14 34 11 11 0 14 11 Average 41 37 43 35 60 38 52 28 37 37 NAD 43 36 46 41 52 56 61 0 41 56 16 The radar below shows the average scores in the nine strategic areas for all 21 local governments. The range of average scores for strategic areas is significantly narrower than the range of scores for local governments. The highest average score is for procurement (60 percent) followed by internal audit (52 percent). The lowest score is for public debt and investment (28 percent) followed by cash management (35 percent) Chart 5: Average PFM scores by strategic area Regulatory framework 100 External audit & oversight 80 Planning & budgeting 60 40 Asset management 20 Cash management 0 Public debt & investment Procurement Internal audit Accounting & reporting Best-performing and worst-performing local governments The highest overall score for financial management is achieved by Aceh Utara (69 percent), while the lowest score is provided by Aceh Jaya (15 percent). The radar below compares the scores for the highest and lowest scoring local governments, illustrating the huge divergence in financial management outcomes across Aceh's local governments. 17 Chart 3: Comparing the best-performing and the worst-performing local governments Regulatory framework 100 External audit & oversight 80 Planning & budgeting 60 40 Asset management 20 Cash management 0 Public debt & investment Procurement Internal audit Accounting & reporting Aceh Utara Aceh Jaya The research team for Aceh Utara identified the political will and commitment of the bupati as the main driver of good performance in financial management. Having well-qualified staff supports efforts to raise financial management capacity. Also, support from the local legislative, NGOs and society groups, encourages the local government to raise its performance. Aceh Jaya's poor performance is in part due to its relatively new status as a district, and the subsequent inadequate human and financial resources at its disposal. In addition, the devastating impact of the tsunami on Aceh Jaya, (the capital, Calang, was completely destroyed) has clearly impacted on financial management outcomes in the medium term. PFM performance in old and recently established local governments More recently formed local governments score lower, on average, for each of the nine strategic areas. Eleven of the 21 district and city governments were formed after 2000. This forms part of a nation-wide pattern of sub-division of districts, together with the formation of fiscally independent city administrations within districts following decentralization. In Aceh there are nine `new' districts and two recently formed city administrations. Lower financial management capacity can result from a number of factors: the lack of government infrastructure in the new district to carry out local government functions effectively (or at least, as well as before the separation); the lack of skilled personnel if most of the civil servants remain in the originating district; the lack of time to develop financial management practices; and, insufficient time to pass supporting regulations. However, newly formed districts and cities do not uniformly score lower than originating districts. Clearly, regional separation needs to be carefully considered to ensure that financial management standards are, at the minimum, maintained. Several of the more recently formed local governments have very poor outcomes, indicating a lack of proper 18 preparation to ensure standards were maintained. Even three to four years after separation, capacity is still far below that of the originating district for several of the recently formed local governments. Chart 4: Comparing performance in old and recently established local governments Regulatory framework 100 External audit & oversight 80 Planning & budgeting 60 40 Asset management 20 Cash management 0 Average old Average new Public debt & investment Procurement Internal audit Accounting & reporting PFM performance in districts (kabupaten) and cities (kota) Prior to the survey, cities may have been expected to perform better than districts for several reasons. First, as urban centre cities may be able to draw on more qualified staff who prefer to live and work in major centers. Cities may have better infrastructure to conduct government functions, particularly compared with neighboring district governments that have been relatively recently formed. The PFM survey results indicate that cities, on average, perform better than districts, although there is one notable exception. Four of the local governments are city administrations. Banda Aceh and Sabang have been separate administrations for some time and Langsa and Lhokseumawe were both formed in 2001 at the start of regional decentralization. A comparison between cities and districts does not show a wide variation, although the average PFM scores for cities are substantially lower than they otherwise would be due to the poor performance of Lhokseumawe (29 percent). Langsa, by contrast, scores higher in every strategic area except external audit, scoring 50 percent overall. 19 4. Detailed Results and Analysis The scores shown above for the nine strategic areas within local governments only provide a glimpse of PFM capacity in these key areas. A more detailed description shows significant variations at outcome and individual indicator level. The proceeding section analyses each strategic area in turn and compares scores outcomes between the local governments at outcome and also indicator level, if insightful. As a detailed analysis of each strategic area in each local government would be overly descriptive given the number of local governments (21) and the number of indicators (256), a comparison of the highest and lowest scores for each area provides the bulk of the analysis. In this way, it is hoped that the worst performing local governments will appreciate the extent to which financial management capacity needs to be upgraded. 5.1 Strategic Area 1: Local regulatory framework In Aceh, as well as elsewhere in Indonesia, a comprehensive legal framework for financial management, in line with national legislation and effectively enforced, is essential in the decentralized context of Indonesia. Since decentralization, local governments are required (Law No. 22/1999 and Law No. 17/2003) to pass local legislation (Peraturan Daerah, known as Perda) to legislate on the managing of finances within the local government. Prior to decentralization, the national law provided a legal umbrella for financial administration, but with the devolvement of fiscal powers and responsibilities to the sub-national level, new supporting legislation is required. Local governments have approached this in a number of ways. Some have pressed ahead and issued Perda in accordance with national obligations, while others have issued SK Bupati decrees (Surat Keputusan Bupati, or SK Bupati) to serve the same purpose, with some still relying on existing national level regulations. The key distinction between Perda and SK Bupati is that Perda need to be passed by the local legislative while SK Bupati decrees are, as the name suggests, issued by the executive without legislative approval. In practice, SK Bupati decrees carry less legal weight and this has implications for adherence and enforcement. The overreaching strategic objective is to create supporting local regulatory frameworks to promote effective financial governance that is consistent with national legislation. The local regulatory framework is divided into three desired outcomes: (1) there is a comprehensive local regulatory framework on local financial management; (2) the framework facilitates effective law enforcement and organizational structure; and (3) the framework includes measures to increase transparency and public participation. While this strategic area focuses on local legislation, including Perda and SK Bupati, other strategic areas are more focused on policies and procedures. For example, outcome one includes indicators on the existence of local legislation on the Regional Medium-Term development Plan (RPJMD) and local legislation on reserve funds and annual budget revisions. Outcome three includes indicators covering transparency and consultation processes. 20 Chart 6: Regulatory framework Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara Regulatory framework Average The average score across all 21 local governments surveyed is 37 percent, below the overall average of 41 percent. Thirteen local governments score poor or very poor. Only two local governments score good. Local regulatory framework - good performers and poor performers Aceh Utara, the highest scoring local government, scores 69 percent for this strategic area. For the first outcome all but two of the 12 indicators are met. Perda are already in place except for legislation on local obligations, and public and private investment. For the second outcome on legal enforcement and structural organization, four of the seven indicators are met. Of the three unrealized indicators, deficiencies include a lack of measurement of performance and a lack of an incentive/sanction structure for staff. For the third outcome on transparency and public participation, Aceh Utara scores 50 percent. While there is evidence of procedures for public participation in budgeting and policy-making processes, there is no formal procedure for bottom- up participation in planning and no legislation on consultation processes or transparency. It should be noted that while the public formally has access to budget sessions in the local parliament, the framework does not capture the extent to which members observe budget sessions. Aceh Jaya has only passed legislation on the annual budget (APBD) and has only passed two SK Bupati decrees in lieu of Perda for all the other 11 indicators of outcome one. Similarly, for outcome two, only one SK Bupati decree is listed, which only partially addresses technical aspects of financial management. Outcome three scores zero, with none of the six indicators met. The total lack of a legal framework to ensure some degree of transparency and community participation is an area of immediate concern. Aceh Jaya's status as a newly formed district may partially explain its low score (20 percent) for local regulatory framework, but the lack of even SK Bupati in lieu of Perda suggests that local governments are either not put under pressure to 21 pass supporting legislation even six years after decentralization or are unable to pass legislation. There are cases of local governments relying on Keppres (Presidential Decree, or Keputusan Presiden). For example, Aceh Barat still uses a Keppres for the procurement of goods and services. In Aceh Barat and Nagan Raya only three of the indicators are met for the outcome on the regulatory framework for financial management. The obstacles and bottlenecks need to be identified and tackled comprehensively, whether these include a lack of impetus from the leadership, a lack of technical expertise or an antagonistic relationship between the local government and the local parliament. 5.2 Strategic Area 2: Planning and budgeting Effective planning and budgeting lie at the core of effective financial management. With poor planning and budgeting systems a local government cannot effectively manage its finances. The strategic objective is the creation of rigorous regional multi-year budgets clearly linked to regional plans. Of the six outcomes, the first outcome on "consistency between bottom-up participative planning processes, regional development, sectoral planning and the annual budget" provides one third of the strategic area score. Chart 7: Planning and budgeting Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara Planning & budgeting Average Planning and budgeting: good performers and poor performers The average score for this strategic area is 43 percent. Nine local governments score poor or very poor. Aceh Utara is the only local government scoring above 60 percent, with a score of 74 percent for planning and budgeting. It scores well for two of the four outcomes. For the first outcome on "consistency between participative bottom-up planning, sectoral planning and budgeting", Aceh Utara meets 14 of the 17 indicators. The RPJMD (Regional Medium-term Development Plan) is judged to be realistic, with clear strategies and programs based on 22 targets. Sectoral planning is based on the RPJMD and reflects development priorities. Minimum service standards are used for budgeting purposes and planning documents and activities in the APBD use a consistent structure. However, planning documents are not supported by project costs in line with budget limitations and planning documents do not cover activities that are funded outside the APBD. Of note, in the regulatory framework strategic area, bottom-up planning processes are not incorporated in local legislation. Outcome two on medium-term budgeting does not score well (only one of three indicators is met). A five-year accountability report is submitted to local parliament but a medium-term expenditure framework is not implemented and a multi-year time horizon is not used in plans and budget forecasts. Outcome three on realistic budget-making process scores relatively poorly, meeting only four of the 11 indicators. The budget is often not approved by the 31 December, a strategy to increase revenue in line with national legislation does not exist, and the differences between planned and realized expenditure and revenue both exceed 10 percent. Bottom-up participative planning scores well, with evidence that the RPJMD is a realistic proposal, while planning documents are based on the RPJMD reflecting development priorities. The budget seems to be pro-poor with all indicators met. Quantitative and qualitative poverty data are collected using a participative approach and pro-poor policies are reflected in the SKPD (Satuan Kerja Perangkat Daerah, or Dinas, work plan budget) and RPJMD. Budget priorities are also broadly pro-poor with spending on public services up from previous years and spending on health, education and infrastructure accounting for about 50 percent of the budget. While there are aspects of planning and budgeting that need to be improved, particularly on medium-term planning and budgeting, Aceh Utara's high overall score sets the standard for other local governments in Aceh for this core aspect of financial management. Aceh Jaya and Nagan Raya, by contrast, score the lowest for planning and budgeting (25 percent). Of the six outcomes, Nagan Raya only scores well for outcome six on expenditure controls to ensure budget output. Outcome one on the consistency between bottom-up planning, sectoral planning and the budget scores very poorly, meeting only two of the 17 indicators. Respondents indicated that village-level meetings (Musbangdes) are not based on community needs, that bottom-up planning proposals contain an unrealistic number of items and that sectoral plans are not based on the RPJMD and fail reflect development priorities. Other weaknesses include a lack of consistency in the structure of planning documents and activities in the APBD and a lack of measurable indicators. Outcome two on medium-term planning scores zero and for outcome three on realistic budget making processes only one of 11 indicators is met. Budgets are not approved on time (the 2006 budget was approved in May 2006, five months late), monthly and quarterly revenue projections are not provided in the budget, there is no strategy to increase revenue and regulations on the use of emergency funds and off-budget funds are unclear. The budget is partially pro-poor, with Nagan Raya meeting four of the nine indicators. Poverty data are lacking, although pro-poor policies are reflected in the Renstra (Rencana Strategis, or Strategic Plan) SKPD and RPJMD. Expenditure on public services has increased in the past three years and expenditure on health, education and infrastructure constitutes the largest share of the budget.3 Outcome five on a comprehensive participatory monitoring and evaluation system for planning and budgeting processes scores poorly, meeting only two of the nine indicators. The public is not involved in the monitoring and evaluation of activities, there is no local legislation on a planning and monitoring evaluation system, and planning and budgeting documents are not publicly disclosed or made easily accessible to the public. 3Budget data are unavailable for Nagan Raya, Bener Beriah, Aceh Jaya and Aceh Singkil districts (APEA, 2006); hence this response cannot be verified. 23 With nine of the local governments scoring well below even moderate levels, this core component of financial management is a priority if financial management outcomes are to be improved. Clear guidance needs to be provided to local governments detailing a strategy to improve planning and budgeting outcomes in line with the outcomes listed. Reform in this area is not straightforward and requires an overhaul of not only processes but also of attitudes within the local administration. The fact that budgets are commonly not approved on time, with delays often running well into the following year, needs to be addressed urgently. Not only does this cause problems in planning and implementation, but it reduces public faith in budget processes. Transparency needs to move from being a buzzword in local government administrations towards becoming a reality. Providing budget information regularly, in good time, making it easily accessible and allowing space for discussion and disagreement would be a big step forward. 5.3 Strategic Area 3: Cash management Cash management is accorded a separate steategic area reflecting the importance of institutionalizing proper practices to handle cash in local government. In some ways it should be the most straightforward of the strategic areas in which to achieve a good score, as effective and proper cash management is such a basic component of sound financial management. However, the 21 local governments only average 35 percent (poor), with 14 local governments scoring poor/very poor and only one achieves good. Chart 8: Cash management Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara Cash management Average 24 Cash management: good performers and poor performers Banda Aceh scores the highest for cash management (61 percent). It scores reasonably well across the four outcomes. For outcome one, policies, procedures and controls to manage cash management are partly in place, with the local government meeting six of the 10 indicators. Written guidance on policies and procedures for cash management is provided and backed by local regulations on cash management in line with national regulations. However, routine staff training on cash management is not provided and the Bawasda (Badan Pengawasan Daerah, or Regional Audit Agency) does not carry out an annual cash management compliance review. Cash receipts and payments are managed reasonably efficiently, meeting eight of the 11 indicators. Cash receipts are stored in a nominated bank account on the day of receipt or the following day. A daily reconciliation is made for cash receipts and deposits, and payments over Rp 5 million are not paid in cash but transferred or paid by check. However, a computerized system is still not in place and regular reconciliations are not made of bank accounts, deposits, accounts receivable and accounts payable. Outcome three focuses on the system for billing and collecting local revenues and, with 17 indicators, this aspect is given prominence. Banda Aceh meets 10 of the indicators on locally sourced revenue (pendapatan asli daerah, or PAD). Policies for local levies and taxes are set out in local legislation, which is consistent with national legislation. The local revenue base is reviewed annually to calculate revenue capacity for each revenue item. Customers are billed on time and a service is provided to handle enquiries from taxpayers. However, the receipting system is inadequate to prevent fraud and it lacks clarity in the event of disputes. Also, billing and collection systems are not integrated and sanctions are not applied to outstanding debtors. Aceh Jaya and Aceh Barat Daya score the lowest (14 percent). Aceh Barat Daya does not manage to meet any of the indicators on policies, procedures and controls to manage cash. This should be partly offset by the use of SK Bupati decrees instead of local regulations to govern the management of cash. Hence, a legal framework is provided, albeit not institutionalized through the issuance of local regulations. Outcome two on cash receipts and payments scores four from 11. Cash receipts are stored in a nominated account and payments over Rp 5 million are transferred to a bank account. Contractors are paid in accordance with requirements and regular reports on cash balances are submitted to the bupati, treasurer and head of the finance department. However, cash is often not stored on the day of receipt, there is no daily reconciliation of receipts and deposits, and cash surpluses are not regularly placed in short-term investments. For outcome three on the system of billing and collecting local revenues, Aceh Barat Daya only meets two of the 17 indicators. Regulations and guidance are lacking, again with a reliance on SK Bupati decrees in lieu of Perda. Account notices are not delivered to taxpayers, a receipting system is not in place to prevent fraud, payments are often not collected on time, penalties are not imposed for late payment and billing and collection systems are not integrated. Outcome four on PAD scores zero. 5.4 Strategic Area 4: Procurement of goods and services The overarching strategic aim is to promote the efficient, competitive procurement of goods and services through policies, procedures and controls. Outcome one, with 47 indicators focuses on value for money in regional expenditure, transparency and accountability in procurement activities. Outcome two, with three indicators, concerns a complaint-handling system. 25 Chart 9: Procurement Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara Procurement Average Procurement: good performers and poor performers With an average score of 60 percent procurement is the highest scoring strategic area. Twelve local governments score acceptable or good and only three score poor. Aceh Utara scores the highest once again (78 percent) and Lhokseumawe scores the lowest (32 percent). Aceh Utara scores very highly for outcome one. There is a local regulation in place to govern the procurement of goods and services, formal guidance on how to conduct procurement is provided, procurement plans are produced annually, estimated costs are prepared and bid documents are kept confidential. However, the unmet indicators are crucial to ensure good procurement practice. DPRD members routinely participate in procurement committees, less than 75 percent of procurements are completed using public bids and there is no rule and/or enforcement governing the participation of procurement committee members and officials with familial relationships with the official appointing them. The second outcome is fully met concerning the operation of a complaints procedure. A Perda governs the complaints procedure and complaints are registered and processed in line with the Perda. In Lhokseumawe, regulations governing procurement are lacking, guidance on procedures is lacking, costs of all procurement plans are not prepared and revised annually, and procurement staff lack qualifications and competence. On the plus side, tender documents are kept confidential, briefing sessions are conducted openly, and announcements on procurements are published in the media. However, there is no system for handling complaints. Despite the often high scores, this does not necessarily mean that procurement processes are conducted transparently and efficiently. The PFM framework only captures the environment of procurement practices and does not evaluate the practice of procurement in each district and city. Although procedures may exist, adherence may remain weak and leakages and corruption can, of course, take place in an environment where adherence and enforcement is weak. However, some local governments have clearly undertaken efforts to improve this much- 26 maligned area of government activity. A first step is to create the legal framework, enforce procedures and then rigorously follow up suspected anomalies. 5.5 Strategic Area 5: Accounting and reporting Accounting and reporting are inescapable components of financial management. This area requires well-defined procedures and staff trained to record financial data. The strategic aim is to establish an accounting system that ensures prompt accounting of all financial transactions and produces reliable, fair and timely external and internal financial reports. It comprises four outcomes: human and institutional capacity; integrated accounting and reporting systems; prompt and accurate recording of all local government financial transactions; and, reliable financial management information reports. Chart 10: Accounting and reporting Aceh Utara Bener Meriah 100 Banda Aceh Aceh Barat Daya 80 Aceh Besar Lhokseumawe 60 Simeulue 40 Nagan Raya Aceh Timur 20 Aceh Tengah 0 Langsa Aceh Tamiang Singkil Aceh Selatan Pidie Aceh Barat Gayo Lues Sabang Bireuen Aceh Tenggara Accounting & reporting Average Accounting and reporting: good performers and poor performers Accounting and reporting scores below the overall average (38 percent compared with 41 percent). Again, Aceh Utara and Aceh Jaya provide the outliers, with Aceh Utara achieving a high 63 percent set against only 11 percent for Aceh Jaya. While Aceh Utara has made solid progress, Aceh Jaya has achieved very little, if any, progress in this area since its formation in 2002. Despite its high overall score for accounting and reporting, Aceh Utara does not possess a Regional Audit Agency (Badan Pengawasan Keuangan Daerah, or BPKD) and, hence, it scores zero for outcome one. However, it scores well for the outcome "transactions and balances are accurately recorded on time" and also for "financial reports and management information are reliable". Assets are properly valued and documented, double-entry book-keeping practices are used and accounting records and bank records are periodically reconciled. For outcome 4, 27 balance sheets, budget realization and cash flow reports are prepared and annual financial reports are submitted to the audit agency in a timely manner. Aceh Jaya, by contrast, scores zero for three outcomes. Human and institutional capacity is very weak, accounting and management systems are not integrated and financial transactions and balances are not recorded promptly or accurately. With such weak systems for accounting and reporting, Aceh Jaya needs support in order to put into place the necessary systems and support to develop a skilled staff base. While Aceh Jaya provides a sharp contrast, it is not the only local government in Aceh with very poor outcomes for accounting and reporting. Bener Meriah, Aceh Tenggara, Nagan Raya and Aceh Barat Daya all score below 20 percent (very poor). 5.6 Strategic Area 6: Internal audit An effective internal audit is a crucial aspect of financial management. An effective internal local government audit requires proper record-keeping and efficiency in local government departments, and reduces the scope for corruption and leakages. The strategic objective for internal audit is the establishment and maintenance of an effective and efficient internal audit function. To assess the extent to which this strategic objective is met there are three outcomes: (1) the local government's internal audit agency is organized and empowered to operate effectively; (2) standards and procedures are acceptable; and (3) findings are followed up adequately. The PFM framework can only capture the formal arrangements for internal audit. It does not evaluate the effectiveness of the audit. An internal audit annual report, which finds no evidence of financial inconsistencies or misappropriation of funds, does not imply that the internal audit was conducted properly. Chart 11: Internal audit Aceh Utara Bener Meriah 100 Banda Aceh Aceh Barat Daya 80 Aceh Besar Lhokseumawe 60 Simeulue 40 Nagan Raya Aceh Timur 20 Aceh Tengah 0 Langsa Aceh Tamiang Singkil Aceh Selatan Pidie Aceh Barat Gayo Lues Sabang Bireuen Aceh Tenggara Internal audit Average 28 Internal audit: good performers and poor performers Internal audit scores 52 percent overall. Aceh Timur and Aceh Utara both score 78 percent with Aceh Jaya again achieving the lowest score of 11 percent. In Aceh Timur, roles and responsibilities of the Bawasda are clearly defined and it has the authority to carry out its functions supported by routine staff training. However, staff are under qualified and equipment is inadequate. For outcome two on acceptable standards and procedures Aceh Timur scores well given its follow-up action based on audit findings. Meanwhile, Aceh Jaya only meets the indicators on clearly defined roles and responsibilities, and authority to carry out its tasks. Acceptable standards and procedures are totally lacking and internal audit findings are not followed up properly. 5.7 Strategic Area 7: Debt and investment This strategic area of debt and investment only has one outcome with eight indicators. The strategic aim is to implement careful management of local government debt and investment including the managing of local state-owned enterprises (Badan Usaha Milik Daerah, or BUMD). The desired outcome is to establish and implement policies, procedures and controls for the management of regional debt and investment. Chart 12: Public debt and investment Aceh Utara Bener Meriah 100 Banda Aceh Aceh Barat Daya 80 Aceh Besar Lhokseumawe 60 Simeulue 40 Nagan Raya Aceh Timur 20 Aceh Tengah 0 Langsa Aceh Tamiang Singkil Aceh Selatan Pidie Aceh Barat Gayo Lues Sabang Bireuen Aceh Tenggara Public debt & investment Average Debt and investment scores only 28 percent, the lowest among the strategic areas. Several local governments have neither accrued debt nor do they engage in long-term investment. For example, Aceh Barat Daya, which scores 25 percent, has no record of debt and investment in its relatively short history. Seven local governments have borrowing records: Aceh Barat, Aceh 29 Selatan, Aceh Tengah, Aceh Tenggara, Aceh Timur, Aceh Utara and Banda Aceh. All score above average for this strategic area except Aceh Tengah. Ministry of Finance data for 20044 show that local governments borrowed Rp 25 billion, while the provincial government borrowed Rp 24 billion. Local water authorities (Perusahaan Daerah Air Minum, or PDAMs) in districts and cities borrowed an additional Rp 40 billion. Total outstanding debt reached Rp 66 billion for local governments in 2004. Total borrowing increased from Rp 55 billion in 2001 to Rp 90 billion in 2004 (local and provincial governments combined). The increase comes solely from local governments with no additional provincial government debt. Despite the increase, accumulated debt remains well below the national provincial average. National law limits total permissible arrears, so some local governments would be precluded from additional borrowing. Even with the restrictions, local governments in Aceh can borrow up to Rp 500 billion (see: Aceh Public Expenditure Analysis, World Bank, 2006). Debt and investment: good performers and poor performers Aceh Utara scores the highest (63 percent) and Aceh Tengah scores the lowest (13 percent) of all local governments with a borrowing record. Five other local governments score zero, with no framework for managing debt and investment. In Aceh Utara, roles and authorities of local parliament members and government officials are clearly defined, the annual budget includes proposed borrowing and long-term investments, long-term investments must be approved by local parliament, and debt and investment transactions are promptly reported in financial records to the bupati. However, management policies are inconsistent with the national policy framework, there are no specific controls on borrowing levels and there are no policies to specify the purposes for which loans and guarantees can be made. In Aceh Tengah only one of the eight indicators is met: the local parliament must approve long-term investment transactions. Given the scope for local governments (and the provincial government) to borrow and invest, it is important that governments have a framework in place to effectively manage their debts and investments. Given the relative size of the financial flows to Aceh's local governments in the coming years, it is all the more important that local governments develop clear strategies in order to make effective longer-term investments. 5.8 Strategic Area 8: Asset management The strategic objective for asset management is for the effective management of regional assets through the utilization of long-term asset management plans. The emphasis is explicitly on long-term management and these assets should support local service-delivery objectives. The framework does not measure the value of the assets to the local economy, or whether they are net contributors or net recipients of revenue but it does assess the ways in which these assets are managed. Capacity in asset management is divided into four outcomes: outcome one concerns procedures and mechanisms for ensuring local enterprises are effectively governed; outcome two concerns policies, procedures and controls for the acquisition of new assets and the effective management of long-term assets; outcome three concerns an information base for supporting asset management; and outcome four concerns the links between asset management and plans and budgets. 30 Chart 13: Asset management Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara Asset management Average Asset management: good performers and poor performers The average score is 37 percent. Aceh Utara yet gain scores the highest for asset management (68 percent). Aceh Jaya and Aceh Barat Daya score the lowest (14 percent). Aceh Utara scores well for outcome one, with proposed activities of local government-owned enterprises consistent with strategic development plans, draft business plans are evaluated by the local government when considering the establishment of new enterprises and transactions of enterprises are reviewed by internal auditors. Outcome two scores poorly, with two of the three indicators not met. Aceh Utara does not have local legislation prescribing policies and plans for the management of local property and it also does not have a comprehensive asset management and procedure manual for asset management guidance. Outcome three is largely achieved, with adequate physical description of assets provided along with the proper recording of assets. Outcome four, with only one indicator, "district plans and budgets reflect maintenance costs of assets is recorded in maintenance plans", is unrealized. Aceh Barat Daya scores zero for outcomes one, two and four. For outcome two concerning policies, procedures and controls it scores zero because the local administration relies on a Ministry of Home Affairs Decree (Kepmendagri) and SK Bupati rather than creating new Perda. Outcome three scores better, as assets are given a unique identification number, the location of assets is properly recorded and the names of the responsible officials are recorded. Every other indicator for the strategic area of asset management is unrealized. Since separation from Aceh Barat, most of the assets within the newly formed district are still under the authority of the original district. No locally-owned enterprises are currently listed although formation and selection are underway. Kota Lhokseumawe also scores poorly (18 percent) but this low score is partly offset by the total lack of locally owned enterprises by the end of 2006 and in the medium-term development plan there are no plans to form locally-owned enterprises. Aceh Utara, the `mother' district, maintains control of all locally owned enterprises. The frequent replacement of the city mayor and department heads has resulted in a lack of strategic planning 31 in this area. Other government assets, such as offices, are inadequate and procedures to ensure the upkeep of assets are lacking. Twelve local governments in Aceh score below 40 percent (poor/very poor) for asset management. This means more than half of the administrations are currently failing in this area of financial management. The poor financial management of district-owned assets means these assets are under-performing. This is of particular concern given the scale of reconstruction in Aceh and the importance of maintaining these newly acquired assets. Capacity needs to be developed in this area and, as a matter of some urgency, regulations and policies need to be put in place and implemented to ensure local governments can properly manage these assets. 5.9 Strategic Area 9: External audit An effective external audit mechanism plays a key role in creating and maintaining an accountable local government. The state audit agency (Badan Pemeriksaan Keuangan, or BPK) is tasked with carrying out external audits and the results of its audits are made available to, and supposed to be discussed by, the local parliament. A key role of the local parliament is to provide independent oversight of the functions of the local government, the executive. The weaker the internal audit the more important the role of the external audit. External audit has two outcomes and nine indicators. Outcome one concerns the implementation of regular external audits to provide effective accountability of local government. Outcome two focuses on the existence of an effective independent oversight of local government financial management. Chart 14: External audit and oversight Aceh Utara Aceh Jaya 100 Banda Aceh Bener Meriah Aceh Besar 80 Aceh Barat Daya Simeulue 60 Lhokseumawe 40 Aceh Timur 20 Nagan Raya Langsa 0 Aceh Tengah Singkil Aceh Tamiang Pidie Aceh Selatan Gayo Lues Aceh Barat Bireuen Sabang Aceh Tenggara External audit & oversight Average 32 External audit: good performers and poor performers The average score for external audit is 36 percent. Three local governments score acceptable and 13 score poor/very poor. Banda Aceh, Aceh Besar and Aceh Utara all score 67 percent meeting six of the nine indicators. Aceh Barat and Nagan Raya do not meet any of the indicators, scoring zero for external audit. Aceh Besar meets three of the four indicators for outcome one. Annual financial statement are submitted for audit to the BPK within the legally required time frame, the public can attend the local parliament session when audit reports are discussed and the external audit report contains an unqualified audit opinion. However, audit reports are not published in the local media or shown to the public on an official announcement board. For the desired outcome of effective independent oversight, the DPRD monitors and evaluates the local government's performance, approved the last annual report without reservations, either did not issue sanctions or ensured sanctions were enforced and audit reports have not sought to initiate corruption investigations. Nagan Raya and Aceh Barat have no external audit. Although the scores for internal audit are above 60 percent in both districts, the complete lack of any mechanism for an external audit by an independent body is of concern. 33 5. Key issues · Incomplete legal framework Five years since the implementation of decentralization, financial management capacity remains weak in most local governments in Aceh. An immediate priority for local governments is to ensure that they have a legal framework in place that is complete, entirely appropriate and enforceable. Financial management practices need to adhere to these regulations and good practice should become the norm--part of the culture of local government. The issuance of SK Bupati decrees and a reliance on previous national level Keppres are both unsatisfactory, as these bypass the local legislative. In particular, SK Bupati decrees are not properly discussed and debated before being issued. As a result, they are likely to fail to become part of the culture of the local legal framework, particularly as a new bupati/walikota may not recognize previous SK Bupati decrees. As such, they are an unsatisfactory short cut to meeting the legal obligations set at the national level. · Lack of qualified and skilled staff Inadequately qualified and/or trained staff constitute a major obstacle to achieving good performance. The research team in Aceh Utara identified good quality human resources as a key factor in driving good financial management outcomes across a number of strategic areas. On-site training may be useful to provide skills, for example, in computerized book-keeping. While additional staff training provided by either the local government itself, or the national government or other agencies, may be useful, the underlying issue is to encourage and, if necessary, assist local governments in attracting candidates with the right technical skills for effective financial management. The long- term solution is to train candidates to a minimum identified standard before they enter the civil service and subsequently to ensure that selection and promotion of civil servants are based on ability and competence for defined roles. This is even more important for the internal audit body, which clearly needs employees with a high level of competence in financial management. Related to this, a clearly defined incentive and sanction structure for staff should be established and strictly adhered to in order to encourage improvements in staff performance. · Lack of financial resources Lack of financial resources to purchase equipment such as computers will reduce the scope for improvements in financial management capacity. Respondents often identified this as a hindrance to good financial management outcomes. However, as identified in the Aceh Public Expenditure Analysis,5 routine expenditure has continued to grow at the expense of development spending. Routine expenditure should clearly be related to improving local government performance. · Lack of transparency Crucial to effective financial management are clear lines of accountability. A key part of this is public participation and public monitoring of finances. Despite assurances, local government financial information is often hard to access for members of the public, media and society groups. While there has been progress in encouraging more participation, higher standards are still not much in evidence across local governments. Where local governments claim to have encouraged participation it remains unclear whether there is any substantive participation. Changing the culture of government in this regard is a long-term project and further progress will be made by bringing pressure on local governments internally, through local media and societal groups. 5Aceh Public Expenditure Analysis ­ Spending for Reconstruction and Poverty Reduction. World Bank, 2006. 34 · Weak internal audit An effective internal audit is probably unrealized even in local governments with a reasonable PFM score. For example, one local government scored reasonably well for this strategic area, but upon brief inspection of the annual audit report the immediate impression was that there had been no effective internal audit. To empower the auditing body, to recruit the right staff, to ensure separation between the auditor and the audited, to ensure anomalies and misappropriations are properly followed up and sanctions applied where proven is, undoubtedly, a daunting task. Yet progress is essential, even more so in Aceh given the scale of funding over the next few years, with oil and gas revenue, reconstruction revenue and additional DAU revenue. Mismanagement of these funds would constitute a grave missed opportunity for Aceh. More effective internal audits would, at the very least, go some way in ensuring funds were properly recorded and traceable. · Realistic and pro-poor budgeting While some local governments seem to be making real progress towards creating pro- poor budgets, others pay only lip service to poverty sensitive planning and budgeting, and others not even that. Some local governments do not have the capacity to conduct a detailed poverty analysis and lack the capacity to ensure budgets really are pro-poor. Also, the frequently wide gap between planned and realized expenditure over several budget cycles illustrates a lack of capacity in developing realistic budgets. · Regional separation Aceh Utara and Lhokseumawe provide an insightful comparison as they score very differently (69 percent compared with 29 percent) even though they formed the same district five years ago. In addition, Aceh Utara, has achieved relatively good outcomes despite its relative poverty. While this survey has not sought to relate financial management outcomes with poverty rates or other indicators it is, nevertheless, notable that good outcomes have been achieved despite a relatively high poverty rate. Many of the respondents point to a high level of political will and commitment from the local government leadership as a key driver of financial management reform rather than strong economic indicators. Government reform efforts have been supported by the legislative body, NGOs and community groups according to the qualitative findings of the research team. This contrasts with several of the lower-scoring local governments which, at the time of the survey, did not have a definitive bupati (i.e. an elected bupati with a five-year term of office). Lhokseumawe still does not have a definitive walikota (city mayor) five years after administrative separation from Aceh Utara. The tug-of-war between Aceh Utara and Lhokseumawe has, according to Lhokseumawe government officials, meant that policy execution has been minimal. Even now, several of the local government departments do not have a dedicated office and are forced to rent office space. In addition, since administrative separation from Aceh Utara, there have been three mayors in Lhokseumawe and each change in leadership has led to a change in leadership across local government departments. One obvious bottleneck this creates is in passing new legislation. More generally, the continuous turnover of leadership from the top down to the level of local government departments severely reduces the scope to implement a coherent development strategy. Given the pace of regional separation, not only in Aceh but across Indonesia, this has profound implications. · Provincial and national support Local governments should be given clear guidance on how to take forward the management of their own finances. A piece-meal approach will not be sufficient. While there is clearly a role for individual local government innovation (and this should be supported and information disseminated) there needs to be provincial and/or national 35 guidance to ensure consistency across local governments and to set minimum standards for local governments. For Aceh, the province has a pivotal role and, with the backing of the new provincial government, much can be done to raise the standards of financial management across Aceh. 36 6. Going forward Results generated by the implementation of the PFM framework have been disseminated to the local governments in Aceh. A `road show' in March - April 2007, disseminated the results, along with the results from the Aceh Public Expenditure Review. Each local government is able to judge its own performance against those of its counterparts. Particular weaknesses have been identified, together with practical steps that should be taken to improve capacity in particular areas. It is important to share knowledge between local governments so that local governments that are performing well in particular areas can assist other less well-performing local governments. Development partners could help facilitate this. Horizontal learning between local governments could be more effective in developing financial management capacity than capacity-building interventions by donors and NGOs. Given its reasonably high scores across the strategic areas, Aceh Utara could play a pivitol role in disseminating information on how to raise capacity. A suitable mechanism should be developed to enable effective information-sharing from better- performing local governments to less well-performing local governments. Qualitative research will be conducted in well-performing local governments to establish more precisely why they perform better, together with parallel research into less well-performing districts to better understand the obstacles preventing positive outcomes. Local governments should be supported in taking the initiative in developing financial management capacity. In order to support capacity-building, there is also a role for non- governmental agencies. Close cooperation between these agencies will be essential as the PFM framework is rolled out beyond Aceh and support for capacity building provided. It is suggested that a website be developed specifically for the PFM results so that results can be added and local governments and other actors can access the results. Openness is essential to ensure that local governments remain at the center of these processes. It is also essential that the PFM scores not regarded as a grading exercise among local governments. It is crucial that government officials feel that it is unequivocally in their own best interests to provide accurate responses, if follow-up PFM surveys in the same local governments to collect accurate data are to reflect changes in financial management performance. In the short term, it is advisable to focus on a limited number of areas to achieve tangible results within a limited time frame. Suggested areas include Planning and Budgeting, a key area and one in which many local governments score poorly. Given the scale of fund flows to local governments in Aceh this is an area of weaknesses that needs urgent attention. Other areas should include those that can be improved comparatively easily. For example, if local governments have a strong regulatory framework there might be scope to transfer this to other local governments relatively easily. Local governments can also be provided with incentives to develop capacity. Improvements in financial management capacity could be linked with revenue, either through DAU funds (the 2 percent dana otsus) or even through earmarked funds such as the DAK. For example, if a local government were able to prove that it had improved its capacity to manage its own finances then additional funding could be provided. In order to make this viable a mechanism is required whereby it is always in the respondents' best interests to answer truthfully. 37 Annex 1. The PFM Framework: Strategic Areas and Outcomes Strategic area Outcomes No. of indicators 1 Local regulatory framework A comprehensive local regulatory framework required by national 12 legislation on local financial management exists. The local regulatory framework provides for an effective law enforcement 7 and organizational structure. The local regulatory framework includes measures to increase 6 transparency and public participation. 25 2 Planning and Budgeting A consistent link between bottom-up planning processes, local 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 3 Budget outturns are reasonable and indicate realistic budget making 9 processes. Budgets are pro-poor. 8 A comprehensive participatory monitoring and evaluation system for 9 planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 53 3 Cash management Policies, procedures and controls to promote efficient cash management 10 are in place. Cash receipts cash payments and temporary cash surpluses are 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 17 established. Local-owned revenue is well managed 6 44 4 Procurement Policies, procedures and controls to promote efficient and competitive 47 procurement of goods and services are established and implemented. 38 Complaints handling system is operating. 3 50 5 Accounting and Reporting Adequate human and institutional capacity for accounting and finance 7 functions exists. Accounting and management information systems are integrated. 3 All local government financial transactions and balances are recorded 9 promptly and accurately. Reliable financial and management information reports are produced. 8 27 6 Internal Audit The local government's internal audit agency is organized and 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 11 Internal audit findings are followed up adequately. 2 18 7 Public Debt and Investment Risk-based policies, procedures and controls for management of local 8 borrowings and investments are established and implemented. 8 8 Asset management Procedures and mechanisms for ensuring effective governance of local 10 enterprises are established. Policies, procedures and controls for acquisition of new assets and 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 8 maintained. Asset management is linked to plans and budgets. 1 22 9 External audit and oversight External audits provide effective accountability of local government. 4 Effective independent oversight of local government financial 5 management exists. 9 256 39 Annex 2: Complete Framework: Strategic Areas, Outcomes and Indicators STRATEGIC AREA 1: LOCAL REGULATORY FRAMEWORK STRATEGIC OBJECTIVE: Creation of supporting local regulatory frameworks to promote effective financial governance that are consistent with national Legislation INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Confirm if the local legislation have been issued A comprehensive local regulatory framework required by national legislation on local financial (compliance with national legislative framework) management exists Local legislation on compilation of planning documents and public consultation processes exists Local legislation: Local legislation, SK/Peraturan Kepala Daerah (Decree) Local legislation on Local Medium Term Development Plan exists Local legislation on guideline for sectoral work plan, sectoral budget (RKA-SKPD) and implementation exists Local legislation on annual budget and budget revision exists LOCAL BUDGET Local legislation on Budget Execution Accountability Report (LKPJ) exists Local legislation on guideline for budget compilation, execution, monitoring, reporting, auditing and Check if legislation includes all of the mentioned issues accountability exists Local legislation on reserve funds exists Local legislation on local procurement exists Local legislation on local-owned enterprises exists Local legislation on local taxes, tax share for villages, tax tariffs and local fees exists Local legislation on local obligations exists Local legislation on local private/public investment exists OUTCOME SCORE OUTCOME NO.2 The local regulatory framework provides for an effective law enforcement and organizational structure 40 Local legislation on financial management is supported by technical working guidelines Check for technical guidance (juknis/juklak) Local legislation on financial management is internally socialized in a timely and comprehensive Timely: Within 2 months after passing manner Comprehensive: all related working units were included in socialization Responsibility for implementation of local legislation clearly defined and confirmed in annual statement Does the LPJ provide for information on of accountability by Regent/Mayor to local parliament implementation of local legislation? Clear delineation of financial management roles, responsibilities and delegations for local parliament, Check local legislation on financial management for Regent/Mayor and local officials in local legislation with specified with financial limits where appropriate EXPLICIT delineation of roles etc. An integrated organizational structure for PFM is implemented (BPKD format) BPKD format includes integration of Expenditure Unit Revenue Unit, Treasury and Accounting Staff performance is being monitored based on measurable indicators Measurable: Qualitative and quantitative indicators that reflect performance levels Incentive and sanction structure for staff is institutionalized Review local legislation for incentives/sanctions OUTCOME SCORE OUTCOME NO.3 The local regulatory framework includes measures to increase transparency and public participation Procedures for public participation in the bottom-up planning process are adopted in local legislation Budgeting process includes some participatory elements Examples of these elements might include consultation with civil society, stakeholder forums etc. Participatory elements in policy making processes are established This could include public consultation for draft local regulation through institutions such as stakeholder forums Local legislation on consultations processes includes consultation processes in development planning, Check comprehensiveness of local legislation on budgeting, policy decisions and evaluation of implemented activities consultation processes- all listed activities must be included. Activity could also be a newspaper article on draft budgets where inputs and comments made Local legislation on transparency exists Examples of this could include availability of documents on planning, budgeting, procurement etc. The public has access to budget sessions in the local parliament This access could be of physical nature or through radio etc. OUTCOME SCORE STRATEGIC AREA 1 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 26 41 STRATEGIC AREA 2: PLANNING AND BUDGETING STRATEGIC OBJECTIVE: Creation of rigorous regional multi-year budgets clearly linked to regional plans INDICATOR YES NO GUIDANCE OUTCOME NO. NO. 1 Consistent link between participatory bottom-up planning process, local development plans, sector plans and budget exists Bottom-up planning process is based upon development plans and priorities Check if any information on plans/priorities has been provided to villages before bottom-up starts Bottom-up planning outcome does not include an unrealistic number of proposals ("Shopping List") Unrealistic ­ more than 3 proposals per village for bottom-up planning outcome The medium-term local development plan is a realistic document and strategies, programs (and Can the objectives be achieved by these activities and activities) relate to the objectives programs? Or are they very broad and general. Check with planning documents Sector plans are based on the medium-term development plan and reflect development priorities Budgets are based on adopted minimum service standards set out in plans Are the Minimum Service Standards considered? Plans and activities in the budgets employ a consistent structure Is the consistency clear? Check DASK of selected agencies and plans Annual budget policy includes measurable outcome indicators Budgets include measurable outcome indicators that refer to programs/strategy Do the outcomes defined relate to respective programs? Check DASK of selected agencies and plans Development plans include cost projections and take overall budget constraints into account Development plans and budgets include activities funded by non local budget funds Check if "deconcentration" funds are documented and included in plans and budget Plans and budget ceilings are based on the same set of realistic on common financial revenue Check with Finance Unit if budget ceilings exist at all projections and what is its basis Budget ceilings for each sector are determined before the budgeting process starts that are in line with When are budget ceilings determined? Check with planning and budget priorities selected sector Consistency between plans, budget and accountability report is evident Evident:: consistency in format and substance can be seen at glance Integrity review is being done between plans/budget/accountability report in accordance with specified Are Bappeda/respective sectors conducting any assignments reviews of integrity? Local legislation regulates clear compulsory working guidelines for the Executive Budget Committee for Check the working basis for Executive Budget the budgeting process Committee 42 Local parliament has been informed about sector programs and sector priorities Important to assess the quality of budget sessions. Does the parliament know about sector programs and priorities that were not passed as local legislation? Local parliament discusses promised outcomes when accountability speech by Regent/Mayor is Check with legislative/executive if discussion is delivered outcome oriented OUTCOME SCORE OUTCOME NO.2 Budgets are based on a medium-term time horizon Medium-term expenditure framework (MTEF) is implemented Stipulated by law 17/2003, basis for multi-year budgeting A multi-year time horizon is used in plans and budget forecasts Is there any medium-term budget consideration at all? Check with Finance Unit 5-year accountability report to local parliament also refers to planned and realized revenue and expenditures OUTCOME SCORE OUTCOME NO.3 Budget outturns are reasonable and indicate realistic budget making processes Budget is approved within time limit specified in budget calendar Approval by Dec. 31 at the latest Monthly and quarterly revenue projections are provided in the budget Check local budget Strategy for revenue increase exists that is in line with national legislation Is there a strategy on how to increase PAD? Local legislation might have been approved by MoHA or MoF Variation of total expenditure as % of budgeted expenditure is less than 10% Off-budget funds-especially deconcentration funds Variation of total revenue as % of budgeted revenue is less than 10% Check for years 2003-2005 as new budget format has been introduced for 2003, making comparison with older data difficult Average budget deficit over the past 3 years is less than 5% Check local budget and consult with Finance Unit The rules for governing the use of contingency funds is clear Is there any guideline on contingency funds? Check with Finance Unit The actual use of contingency funds is accounted for adequately Any reporting? Check local budget, accountability report Clear rules for in-year budget flexibility exist Only possible with permission of local parliament? Authorization of use of funds outside the budget is clearly regulated Who is keeping track of off-budget funds, especially deconcentration funds? Subsides for locally-owned enterprises are recorded in the operational budget 43 OUTCOME SCORE OUTCOME NO.4 Budget to be pro-poor Poverty assessment has been conducted using qualitative and quantitative data and households, Basis for poverty programs if any? groups and localities that are poor, vulnerable or have unequal access to public services are identified Participatory methods and approaches were used to collect data and input from low income households, groups and localities that are poor, vulnerable or have unequal access to public services Specific reliable data on the multi-dimensional aspects of poverty is available and reflected in the Various sources of local poverty data at Dinas, priorities of development plans, especially for sectors like health and education BKKBM, NGO's and national level exists (SUSENAS, PODES). What data has been used? Pro-poor policy exists and is reflected in sector plans Local poverty reduction strategy is required by national government, but local governments have different approaches (Renstra miskin etc.) Budget priorities reflect pro-poor policies and priorities Check in budget policy (AKU) and annual plan Pro-poor expenditure can be explicitly identified as such in the budget Check if activities in the budget are earmarked as pro- poor Expenditure for public services have increased over the past three years The ratio between apparatus expenditure and public expenditure has increased over the past three years Budgeted expenditure on health, education and infrastructure account for the largest share in the % of overall expenditure per sector in aggregate budget (in aggregate) Relevant village block grants have been established How big are the grants per village? Relevant - At least Rp. 10-20m available for development activities OUTCOME SCORE OUTCOME NO.5 Comprehensive participatory monitoring and evaluation system for planning and budgeting process is established Planned activities not taken up in the budget are reviewed and are included during budget revisions or What happens with the planned activities not being the subsequent budget year budgeted? Each sector holds record of planned and realized activities, including realized budget vs. planned Check with selected sectors if they keep track of budget expenditure developments Budget outcome indicators are measured at least every six months Verify with Finance Unit Sector performance reports and responsibility reports are verified by Internal Audit Agency Ask internal audit unit for report and their audit plan Record of activities being budgeted that what is decided upon during bottom-up process is brought Any evaluation? back and made public to villages and sub-districts Planning and budgeting documents are publicly disclosed and easily accessible by the public Where announced? Comprehensive budget progress reports are compiled and submitted to the Regent/Mayor Do budget progress reports exist? 44 Planning and budgeting monitoring and evaluation system is authorized by local legislation Consult with Bappeda, Finance Unit and/or Legal Office The public is involved in the monitoring and evaluation of implemented activities and this participation Check for participatory elements in the M&E and its is institutionalized institutionalization OUTCOME SCORE OUTCOME NO. 6 Expenditure controls are in place to maximize budget output The Local Government uses a quarterly SKO system Check SKO, SPMU, SPM and SPP Work units use a SKO to propose payments (SPP and SPM) The Local Government uses set output criteria for work units' activities No work units exceed the budget in proposing budget revisions OUTCOME SCORE STRATEGIC AREA 2 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 53 45 STRATEGIC AREA 3: CASH MANAGEMENT STRATEGIC OBJECTIVE: Implementation of effective cash management practices to ensure efficient management of funds for service delivery INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Policies, procedures and controls to promote efficient cash management are in place Written guidelines on cash management policies and procedures exist Cash management policies exist; these require collecting and banking receipts promptly, making payments when they are due and providing accurate cash flow forecasts Local legislation has assigned specific cash management duties to particular officials Check whether the institutional arrangements in sections 2 to 4 have been established in local legislation Delegations of authority are made for approving cash payments Accommodated in local legislation? Procedures for authorization of signatories to bank accounts are specified Accommodated in local legislation? Procedures for establishment of bank accounts are specified Accommodated in local legislation? Procedures for operation of bank accounts are specified Accommodated in local legislation? Procedures for making payments to suppliers of goods and services are specified Accommodated in local legislation? Local cash management legislation is consistent with national policy framework Check if local legislation is consistent with Law 1/2004 Regular relevant training for cash management staff is conducted Regular: at least annually Relevant: training on new national legislation Internal Audit Agency undertakes annual cash management compliance review Any report existing? Check with internal audit unit OUTCOME SCORE OUTCOME NO. 2 cash receipts, cash payments and temporary cash surpluses are managed and controlled efficiently All receipts are deposited into a single bank account or alternatively funds are pooled in the Treasury Check with treasury All cash receipts are banked on day of receipt Check with treasury staff and ask for proof Daily reconciliation of cash receipts and cash deposits Ask for reconciliation sheet 46 Basis for assessment of local revenues is determined by revenue department (this does not apply to Check with revenue department or Financial street lighting tax) Management Unit All payments in excess of 5 million rupiah are generally made by bank transfer Check whether the following features of good accounts payable management are applied Payments to contractors are made in accordance with contractual terms and conditions Check if contracts include payment modes Record keeping for payments and receipts at the treasury are computerized Is there any software or manual input? Cash flow forecasting undertaken for rolling periods and variances analyzed Review the frequency with which cash flow forecasts are prepared Regular reconciliations of bank accounts, short-term deposits, accounts receivable and accounts Check for timing of reconciliations payable records with general ledger balances Cash surpluses are regularly identified and placed in short-term investments in accordance with stated Is there any action on cash surpluses? Bank deposit? policy Check if there is a policy on this Regular reports on cash balances provided to the Regent/Mayor, local treasurer and head of finance Is head of region informed about cash balances? Ask for report OUTCOME SCORE OUTCOME NO. 3 An efficient system for billing and collecting local revenues is established Policies for local levies and taxes are set out in local legislation Check content of local legislation on taxes and fees Details of arrangements for the administration of local levies and taxes are set out in a revenue manual Does a revenue manual exist at all? Check with Revenue unit or financial management unit Local revenue management legislation is consistent with national policy framework Is the local legislation on taxes and fees approved by MoHA and MoF? Detailed supporting billing information is available on each local taxpayer Details of the name, address, reference number and amount billed is recorded for each local taxpayer Local revenue tax base is verified annually Check with Revenue unit or financial management unit whether annual verification is undertaken Accurate account notices are produced on a timely basis and delivered promptly to local taxpayers Ask for copy of notices at revenue unit or financial management unit Local levy and tax account notices are checked prior to being delivered to local taxpayers Verify with the person in charge A sound receipting system is used to prevent fraud and ensure clarity in the event of disputes Computerized and comprehensive? Easy to fraud? Check receipts and look at revenue unit or financial management unit Payments from customers are collected relatively promptly Promptly: at the latest within one 1 week after the due date Verify with staff from revenue unit, financial management unit and ask for documentation Billing and collection systems are integrated Verify at revenue unit or financial management unit Management information about outstanding debtors is able to be produced promptly Promptly: immediately and at all times. Verify at revenue unit or financial management unit 47 Penalties are imposed on late payments of local levies and taxes Verify at revenue unit or financial management unit A firm approach is employed in following up outstanding debtors Any penalties or commonly applied procedure? Verify at revenue unit or financial management unit A service for addressing taxpayer queries is provided Verify at revenue unit or financial management unit Monthly reconciliations of bank deposits and revenue collection figures is conducted by accounting Verify at revenue unit or financial management unit officials Appropriate training given to revenue staff Appropriate: Training on computer, revised legislation? Internal audit unit annually reviews revenue administration procedures Check with internal audit unit and ask for report OUTCOME SCORE STRATEGIC AREA 3 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 38 48 STRATEGIC AREA 4: PROCUREMENT STRATEGIC OBJECTIVE: Increase the efficiency in regional procurement activities that foster increased competition, provide improved value for money in regional expenditure, create more transparency and result in greater accountability INDICATOR YES NO GUIDANCE OUTCOME NO. 1 policies, procedures and controls to promote efficient competitive procurement of goods and services are established and implemented Adopted local legislation on procurement consistent with Presidential Decree 80/2003; Presidential Check legal basis of procurement local legislation Decree 61/2004 exists and no contrary procurement legislation exists Local legislation has assigned specific responsibilities and duties for the commissioning and Check procurement local legislation undertaking of procurement and for the exercising of overall responsibility for procurement to particular officials Local parliament members do not participate in procurement committees in any manner Check whether local legislation prevents local parliament members from participating Procurement committees have the minimum required number of members prescribed in local legislation Check whether the procurement committee is operating on procurement and the members are certified effectively Procurement committee members are selected using a process prescribed in local legislation Does the local legislation include regulations on committee members? A local procurement manual that provides guidance on all procurement forms, mechanisms, Check whether a procurement manual exists and procedures and processes has been prepared addresses these matters Contracts are only signed after proposed expenditure has been included in the latest approved budget Procurements are linked to approved budgets and available funding All work units purchasing external goods and services compile annual procurement plans for approved Check scope of procurement planning budgeted activities Estimated prices prepared for all planned procurements are prepared and at least annually revised Check with Public Works on this practice At least 75% of procurements by number are completed using public bids Check that most procurements are completed using public bids The procurement committee makes information available to the public Check if and how this is done Committee members only receive gifts openly Where public bids are not used in procurements, it meets the conditions specified in Presidential Check if local legislation on procurement provides for Decree 80/2003 and Presidential Decree 61/2004 this issue Format for presenting and evaluating bids is specified in procurement documentation Check with Public Works and Financial Management Unit. Briefing sessions held for all public bid procurements and attendance record kept Check with Public Works and Financial Management Unit. 49 All bid documents are kept confidential in a secure environment prior to opening Check with Public Works and Financial Management Unit. Contracts that are not awarded to lowest bidder comply with procurement rules Check with Public Works and Financial Management Unit. Contractor performance is monitored and reported back to the procurement committee for future Check with Public Works and Financial Management reference Unit. Records kept of all communications seeking clarification of tenders Check with Public Works and Financial Management Unit. Records are maintained of all procurement decisions to assist conduct of procurement audits Any procurement audits undertaken? Procurement documents are compiled and followed up Check the evaluation criteria and if the documents a re discussed with the users Detailed information provided in the debriefing process to unsuccessful bidders is recorded and held on The practice of this issue needs to be checked with file public works or other agency that is heavily involved in procurement. Check with Financial Management unit At least six monthly reports summarizing procurement activities are submitted to Regent/Mayor Check whether these procurement reports are issued All procurement activities are audited by Internal Audit Agency, and results of audit included in regular Check with Internal audit unit and ask for report audit report No serious issues have been raised relating to procurement in Internal Audit Agency reports in the Ask for access to the reports. Cases of Corruption, proceeding years Collusion, Nepotism or other illegal practices? All procurement internal controls and Internal Audit Agency audit reports are followed-up and resolved Check report and documentation on follow-up Local legislation specifies sanctions where procurement officials do not comply with procurement policy Confirm if any sanctions have been applied Rules requiring members of procurement committee and procurement officials to have no family Does this rule exist in a written form? Check local relationship with the official appointing them, are enforced legislation on procurement , code of ethics etc. Guidance is provided to officials on minimizing conflicts of interest Are the officials aware of conflicts of interest? Non-compliant bids rejected and bids associated with irregular actions are rejected Check sample of procurement transactions to confirm whether action has been taken if bidding irregularities Bids made by blacklisted goods and services providers are rejected Action is taken against suppliers found guilty of collusive practices after contracts have been issued Such instances may be evident form Internal Audit Agency audit reports and the register of public complaints Contractual financial guarantees are stated in the tender documents Verify with Dinas PU staff Law 5/1999 on monopolies and unhealthy competition is adhered to Check the existence of KPPU (Committee for oversight of enterprise competition) Proposals for awarding contracts is stated in the tender document Verify with Dinas PU staff Pre-qualification results are publicized in local media and on official announcement boards Is there any announcement board? Check local media clippings 50 Public bid tenders are opened in public Verify with staff from public works or other agency Announcements on procurements are made in local media and on official announcement boards Is there any announcement board? Check local media clippings Briefings provided to unsuccessful bidders for public bids and attendance records are kept Verify with staff from public works or other agency Immovable property to be sold principally on basis of competitive bids or at auction The practice of this issue needs to be checked with public works or other agency that is heavily involved in procurement. Check with Financial Management Unit Proposed contract financial obligations are disclosed in bidding documents Verify with staff from public works or other agency Proposed process for awarding contracts is disclosed in bidding documents Verify with staff from public works or other agency Pre-qualification instructions are criteria are socialized Verify with BAWASDA and external auditor, contractors and public The results of pre-qualification selection are clear Proposed contract financial obligations are disclosed in bidding documents Verify with staff from public works or other agency Procurement staff are qualified and competent There is a project completion process OUTCOME SCORE OUTCOME NO. 2 A complaint handling system is operating Formal complaints process and procedures is provided for in local legislation Check whether the local legislation on procurement includes complaint procedures Complaints are registered Check whether the local legislation on procurement includes complaint procedures Complaints are processed in accordance with procedures set out in local legislation Check whether the local legislation on procurement includes complaint procedures OUTCOME SCORE STRATEGIC AREA 4 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 52 51 STRATEGIC AREA 5: ACCOUNTING AND REPORTING STRATEGIC OBJECTIVE: Establishment of an accounting system that ensures prompt accounting of all financial transactions and produces reliable, fair and timely external and internal financial reports INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Indicators 1-3 only apply for local governments who Adequate human and institutional capacity for accounting and finance functions exists have implemented BPKD. Others automatically score 0 The Financial management unit (BPKD) exists, functions and has sufficient qualified staff Exists: Building, Functions: institutional capacity Qualified staff: Accountants? Check for comprehensiveness of legal basis for Financial Management Unit? Office available? Staff assigned? An integrated organizational structure for FM is implemented (BPKD format) BPKD format includes integration of Expenditure Unit, Revenue Unit, Treasury and Accounting The Financial management unit has clear descriptions for all its functions Local legislation on financial management unit? Technical regulations? Manual on accounting procedures and processes exists Check with head of financial management unit The Heads of each department in the Financial management unit have an accounting or finance Check with head of financial management unit degree At least 10 percent of the Financial management unit staff have a diploma or a higher degree in Check with head of financial management unit accounting The Financial management unit has adequate computer resources to fulfill its mandate Sufficient software, hardware? OUTCOME SCORE OUTCOME NO. 2 Accounting and management information systems are integrated The accounting and management information reports are produced on the same system Check whether the integrated financial information system covers the following activities: budgeting, treasury, revenue, cash, investment, fixed asset, debt, accounting and reporting Accounting and managerial reports are produced using integrated financial management information Reports can be produced on either a user need or system user-defined basis. Performance and external reports can be produced quarterly, semester and yearly Managerial and ad-hoc reports are produced regularly Check whether there are processes to ensure that financial reports are reviewed and action taken when necessary; financial reports are often just documented OUTCOME SCORE 52 OUTCOME NO. 3 All Local Government financial transactions and balances are recorded promptly and accurately Supporting documents for ownership of assets exist Check for: Cash & bank deposit documents , Investment documents. Land, building and vehicle ownership documents Documents for bank and government loan agreements and grants exist Check with Financial Management Unit for existence Tangible assets and external liabilities are verified and valued to provide a basis for determining Check for inventory of Cash, land, building, opening balance sheet balances investment, infrastructure and machinery assets and supporting valuations. Check for inventory of borrowings from banks and central government Double entry bookkeeping practices are applied and accounting trial balances are matched Check this practice with Financial Management Unit staff Opening balance sheet has been made Check this practice with Financial Management Unit staff Cash revenue journals have been made Check this practice with Financial Management Unit staff Cash expenditure journals have been made Check this practice with Financial Management Unit staff General journals have been made Periodic reconciliations of accounting records with bank records. External party records requiring Modest differences: confirmation or reconciliation include investments, deposits, debtors and account payables Less than 5% of reported balances OUTCOME SCORE OUTCOME NO. 4 Reliable financial and management information reports are produced Expenditures are classified by organization, function and economic category Check local budget randomly Internal financial management reports are regularly reviewed by the Regent/Mayor and initiate Check for: Internal reports present budgeted and actual corrective action where required figures and any deviation. Internal reports are presented to manager or decision maker on a timely basis. Managers review internal reports and make decisions based on internal reports Reports on targeted and actual budget inputs, outputs, outcomes, benefits, and impacts are produced Regularly: at least every 6 months regularly and in time In time: within 1 month after period has ended. Check this practice with Financial Management Unit staff Balance sheet is prepared Should be prepared at least six-monthly Budget realization report is prepared Should be prepared at least six-monthly Cash flow report is prepared Should be prepared at least six-monthly 53 Notes are included in the financial statements Should be prepared at least six-monthly Annual financial statements for audit are submitted in a timely manner Local government submits annual report to Supreme Audit Agency within 4 months after end of fiscal year OUTCOME SCORE STRATEGIC AREA 5 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 26 54 STRATEGIC AREA 6: INTERNAL AUDIT STRATEGIC OBJECTIVE: Establishment and maintenance of an effective and efficient internal audit function INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Most of the following indicators need to be clarified with The local government's internal audit AGENCY is organized and empowered to operate effectively Internal audit unit The roles and responsibilities of all internal audit agency officials are clearly defined in local legislation Check whether Local legislation on internal audit exists and if regulates this issue Internal audit agency has the necessary authority for conducting its operations Check whether the internal auditors are authorized to have full, free and unrestricted access to all functions, property, personnel, records, accounts and files. Internal Audit Agency has adequate qualified staff that include some certified auditors and accountants Check with Internal audit unit staff, any staff take-over from financial management unit? Ask for audit certification Regular relevant trainings are conducted Check with Internal audit unit staff. Any training plan? Internal audit agency has adequate supporting operating resources Cars, computers etc. OUTCOME SCORE OUTCOME NO. 2 Internal audit standards and procedures applied are acceptable The internal audit is conducted according to the internal audit plan Ask Internal audit unit staff for Audit plan Internal audit reviews all activities of the local government including any commercial activities Are PDAM and other regional-owned enterprises included in the audit? Internal Audit regularly examines the internal controls of all significant accounting operations that affect Check with Internal audit unit staff, does audit also financial reports include accounting issues. Internal audit programs exist for all local government asset and liability categories and activities Check with Internal audit unit staff Internal audit standards/procedures are documented in an internal audit manual Check whether this manual exists Audit programs are regularly revised and reviewed Verify with Internal audit unit staff Internal auditors maintain independence Check if Internal Audit Agency staff has no family relationship with the Regent/Mayor, local secretary, and head of working units Internal audit reports require findings on deviations from procedures, internal control weaknesses, Check audit reports randomly inefficiencies and fraud and make recommendations for improvement 55 Internal audit reports state scope of work prior to opinion/conclusion Including what was audited, procedures followed, time frame of activities covered, duration of assignment, clarifications or qualifications if any, procedures and tests that could not be carried out, limitation in scope, compliance with applicable legislation Internal audit reports are sent to Regent/Mayor Check with head of region Internal audit reports are available to the external auditor Has Supreme Audit Agency (BPK) audited these reports? OUTCOME SCORE OUTCOME NO. 3 Internal audit findings are followed up adequately Internal audit reports are addressed to managers who have the immediate responsibility for these Check audit reports randomly operations Sanctions have been imposed by regent/mayor following receipt of adverse internal audit findings Check with head of region OUTCOME SCORE STRATEGIC AREA 6 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 19 56 STRATEGIC AREA 7: PUBLIC DEBT AND INVESTMENT STRATEGIC OBJECTIVE: Establishment of prudent management of regional borrowings, regional investments and interests in regional enterprises INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Risk-based policies, procedures and controls for management of local borrowings and investments are established and implemented Local borrowing and investment management policies, consistent with the national policy framework, Check for existence and implementation with financial are implemented management unit staff Accountability is promoted by defining roles and authorities of local parliament members and Does the local legislation on Financial Management government officials, procedures and processes for borrowing and investment management activities include roles and responsibilities? Or does separate together with delegations of authority for borrowing and investment management activities local legislation exist? Proposed borrowing transactions and long term investments in local enterprises are disclosed in annual Check local budget budget Policies specify purposes for which loans and guarantees can be made Check with policy (if existent) Specific controls are introduced that limit the total level of external borrowing outstanding What is the policy on external borrowing? Any controls introduced? Investment policies specify objectives associated with new portfolio investments and long-term Check with Financial Management Unit staff investments in local enterprises Local parliament must approve local government long-term investment transactions by local parliament Check with local legislation on financial management resolution Debt and investment transactions are promptly reported in financial reports to the Regent/Mayor Debt and investment transactions reported to local treasurer on day of transaction OUTCOME SCORE STRATEGIC AREA 7 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 8 57 STRATEGIC AREA 8: ASSET MANAGEMENT STRATEGIC OBJECTIVE: Effective management of regional assets by utilizing long-term asset management plans to ensure that these assets best support regional service delivery objectives INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Procedures and mechanisms for ensuring effective governance of local enterprises are established Proposed activities of local enterprises are consistent with local governments' strategic plans Check RENSTRA/RPJMD if local enterprises are included Detailed draft business plans are considered by local governments when evaluating merits of Do local business plans exist? Does the local establishing new local enterprises government intend to establish a new enterprise? Local legislation on financial management is expanded to include financial management and reporting Check local legislation on Financial Management of local enterprises Annual financial statements on local enterprises are audited by external auditors appointed by local Check with head of randomly chosen local-owned governments enterprise on this issue and verify with Financial Management Unit staff Transactions of local enterprises are reviewed by internal auditors Verify with Internal audit unit Remuneration of commissioners, directors and senior officials of local enterprises must be approved by Check with regional secretary and/or head of local parent local governments enterprise Budgets of local enterprises include supporting performance indicators and measures Check budget of local enterprise Budgets/business plans of local enterprises are approved by parent local governments and boards of Check with regional secretary and/or head of local commissions enterprise Local government appoint non-political appointees as commissioners and directors in all local Check with regional secretary and/or head of local enterprises that are either wholly or partly owned by local governments in accordance with process enterprise prescribed in local legislation Local government has established processes for monitoring performance of local enterprises by Check with regional secretary and/or head of local regent/mayor enterprise OUTCOME SCORE OUTCOME NO. 2 Policies, procedures and controls for acquisition of new assets and effective management of existing long-term physical assets are established and implemented Adopted local legislation prescribes policies and plans for the management of local property including Check local legislation on financial management for non-current physical assets inclusion of asset management. Or separate local legislation? 58 The duties of the officials who have been assigned specific asset management responsibilities are Check local legislation on financial management for prescribed in local legislation this issue. Or separate local legislation? Ask Financial Management Unit for practice Comprehensive asset management policy and procedure manual has been prepared that provides Verify with Financial Management Unit detailed guidance on local asset management activities OUTCOME SCORE OUTCOME NO. 3 Supporting asset management information base is established and maintained Assets physical description is described Check this practice with Financial Management Unit and ask for sample Asset is given unique identification number Check this practice with Financial Management Unit and ask for sample Purchase details is recorded Check this practice with Financial Management Unit and ask for sample Location of asset is recorded Check this practice with Financial Management Unit and ask for sample Name of official responsible for asset is recorded Check this practice with Financial Management Unit and ask for sample Current asset condition is recorded Check this practice with Financial Management Unit and ask for sample Accounting information is recorded (book value) Check this practice with Financial Management Unit and ask for sample Movable assets are physically verified at least once a year and results compared with the records Check this practice with Financial Management Unit and ask for sample OUTCOME SCORE OUTCOME NO. 4 Asset management is linked to plans and budgets District plans and budgets reflect maintenance expenditures recorded in maintenance plans Check annual plan and local budget OUTCOME SCORE STRATEGIC AREA 8 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 22 59 STRATEGIC AREA 9: EXTERNAL AUDIT AND OVERSIGHT STRATEGIC OBJECTIVE: Increase of accountability for financial management through effective and independent oversight INDICATOR YES NO GUIDANCE OUTCOME NO. 1 Regular external audits provide effective accountability of local government Annual financial statements are submitted for audit to Supreme Audit Agency within legally required Verify with financial management unit if financial time frame statements have been sent to BPK If existent, audit reports are publicized in the local mass media and on the official announcement board If no external audit has been conducted in the last two years, no ratings are to be given The public is able to attend local parliament session when audit reports are discussed Verify with DPRD members The external audit report contains an unqualified audit opinion Check audit report if possible, easily accessible? OUTCOME SCORE OUTCOME NO. 2 Effective independent oversight of local government financial management exists Local parliament monitors and evaluates local governments' performance based on financial reports, Check with local DPRD members audit reports and accountability reports Local parliament has approved the last annual report without reservations Are minutes of meeting available? a. No sanctions against officials were recommended by Supreme Audit Agency Answer only question a OR b (whichever is applicable) b. In case sanctions were recommended by Supreme Audit Agency, sanctions were enforced Check with regional secretary No payment of penalty is imposed as consequence of audit finding Ask for Supreme Audit Agency report External audit reports do not suggest to initiate investigations into public sector corruption Ask for Supreme Audit Agency report OUTCOME SCORE STRATEGIC AREA 9 TOTAL SCORE TOTAL ACHIEVABLE SCORE: 9 60 Annex 3: Local Governments Surveyed Banda Aceh ............................................................................................................................................62 Aceh Besar..............................................................................................................................................63 Aceh Barat..............................................................................................................................................64 Aceh Jaya................................................................................................................................................65 Nagan Raya ............................................................................................................................................66 Aceh Timur.............................................................................................................................................67 Aceh Utara..............................................................................................................................................68 Bireuen ...................................................................................................................................................69 Pidie........................................................................................................................................................70 Aceh Tenggara........................................................................................................................................71 Simeulue.................................................................................................................................................72 Singkil.....................................................................................................................................................73 Aceh Taming ..........................................................................................................................................74 Kota Langsa............................................................................................................................................75 Gayo Lues...............................................................................................................................................76 Aceh Barat Daya.....................................................................................................................................77 Aceh Selatan...........................................................................................................................................78 Aceh Tengah...........................................................................................................................................79 Bener Meriah..........................................................................................................................................80 Kota Sabang............................................................................................................................................81 Kota Lhokseumawe................................................................................................................................82 Aceh Provincial Government .................................................................................................................83 61 1 Banda Aceh Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 6 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law enforcement 4 7 and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 48% 25 Planning and A consistent link between bottom-up planning processes, local 8 17 Budgeting development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget making 10 11 processes. Budgets are pro-poor. 3 9 A comprehensive participatory monitoring and evaluation system for 4 9 planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency. 2 4 53% 53 Cash management Policies, procedures and controls to promote efficient cash management 6 10 are in place. Cash receipts cash payments and temporary cash surpluses are 8 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is established. 10 17 Local-owned revenue is well managed. 3 6 61% 44 Procurement Policies, procedures and controls to promote efficient and competitive 32 47 procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 68% 50 Accounting and Adequate human and institutional capacity for accounting and finance 0 7 Reporting functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are recorded 8 9 promptly and accurately. Reliable financial and management information reports are produced. 8 8 59% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable. 6 11 Internal audit findings are followed up adequately. 2 2 56% 18 Public Debt and Risk-based policies, procedures and controls for management of local 4 8 Investment borrowings and investments are established and implemented. 50% 8 Asset Procedures and mechanisms for ensuring effective governance of local 4 10 management enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 5 8 maintained. Asset management is linked to plans and budgets. 0 1 41% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 4 5 management exists. 67% 9 Average 56% 256 62 2 Aceh Besar Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 6 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 5 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 56% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 6 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget making 4 9 processes. Budgets are pro-poor. 6 8 A comprehensive participatory monitoring and evaluation system for 3 9 planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 42% 53 Cash management Policies, procedures and controls to promote efficient cash 4 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 5 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 10 17 established. Local-owned revenue is well managed 2 6 48% 44 Procurement Policies, procedures and controls to promote efficient and 29 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 62% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 3 3 All local government financial transactions and balances are 5 9 recorded promptly and accurately. Reliable financial and management information reports are 8 8 produced. 59% 27 Internal Audit The local government's internal audit agency is organized and 3 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 8 11 Internal audit findings are followed up adequately. 1 2 67% 18 Public Debt and Risk-based policies, procedures and controls for management of 3 8 Investment local borrowings and investments are established and implemented. 38% 8 Asset management Procedures and mechanisms for ensuring effective governance of 0 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 2 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 7 8 maintained. Asset management is linked to plans and budgets. 1 1 45% 22 External audit and External audits provide effective accountability of local government. 3 4 oversight Effective independent oversight of local government financial 3 5 management exists. 67% 9 Average 54% 256 63 3 Aceh Barat Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 1 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 1 6 transparency and public participation. 8% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 3 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 1 9 making processes. Budgets are pro-poor. 5 8 A comprehensive participatory monitoring and evaluation system 1 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 4 26% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 9 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 11 17 established. Local-owned revenue is well managed 1 6 50% 44 Procurement Policies, procedures and controls to promote efficient and 34 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 70% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 1 3 All local government financial transactions and balances are 1 9 recorded promptly and accurately. Reliable financial and management information reports are 3 8 produced. 19% 27 Internal Audit The local government's internal audit agency is organized and 3 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 6 11 Internal audit findings are followed up adequately. 2 2 61% 18 Public Debt and Risk-based policies, procedures and controls for management of 4 8 Investment local borrowings and investments are established and implemented. 50% 8 Asset management Procedures and mechanisms for ensuring effective governance of 5 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 7 8 maintained. Asset management is linked to plans and budgets. 1 1 64% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 0 5 management exists. 0% 9 Average 39% 256 64 4 Aceh Jaya Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 3 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 0 6 transparency and public participation. 20% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 3 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 3 9 making processes. Budgets are pro-poor. 3 8 A comprehensive participatory monitoring and evaluation system 1 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 25% 53 Cash management Policies, procedures and controls to promote efficient cash 2 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 0 17 established. Local-owned revenue is well managed 0 6 14% 44 Procurement Policies, procedures and controls to promote efficient and 17 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 34% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 0 9 recorded promptly and accurately. Reliable financial and management information reports are 3 8 produced. 11% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 0 11 Internal audit findings are followed up adequately. 0 2 11% 18 Public Debt and Risk-based policies, procedures and controls for management of 0 8 Investment local borrowings and investments are established and implemented. 0% 8 Asset management Procedures and mechanisms for ensuring effective governance of 0 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 3 8 maintained. Asset management is linked to plans and budgets. 0 1 14% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 1 5 management exists. 11% 9 Average 15% 256 65 5 Nagan Raya Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 2 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 1 6 transparency and public participation. 12% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 2 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 1 9 making processes. Budgets are pro-poor. 4 8 A comprehensive participatory monitoring and evaluation system 2 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 4 25% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 5 17 established. Local-owned revenue is well managed 0 6 23% 44 Procurement Policies, procedures and controls to promote efficient and 30 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 64% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 2 9 recorded promptly and accurately. Reliable financial and management information reports are 2 8 produced. 19% 27 Internal Audit The local government's internal audit agency is organized and 4 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 6 11 Internal audit findings are followed up adequately. 2 2 67% 18 Public Debt and Risk-based policies, procedures and controls for management of 1 8 Investment local borrowings and investments are established and implemented. 12% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 5 8 maintained. Asset management is linked to plans and budgets. 0 1 41% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 0 5 management exists. 0% 9 Average 29% 256 66 6 Aceh Timur Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 9 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 5 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 68% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 10 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 3 9 making processes. Budgets are pro-poor. 6 8 A comprehensive participatory monitoring and evaluation system 6 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 51% 53 Cash management Policies, procedures and controls to promote efficient cash 5 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 2 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 8 17 established. Local-owned revenue is well managed 0 6 34% 44 Procurement Policies, procedures and controls to promote efficient and 32 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 64% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 4 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 3 9 recorded promptly and accurately. Reliable financial and management information reports are 7 8 produced. 52% 27 Internal Audit The local government's internal audit agency is organized and 3 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 9 11 Internal audit findings are followed up adequately. 2 2 78% 18 Public Debt and Risk-based policies, procedures and controls for management of 4 8 Investment local borrowings and investments are established and implemented. 50% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 0 1 36% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 2 5 management exists. 33% 9 Average 52% 256 67 7 Aceh Utara Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 10 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 4 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 68% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 14 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 9 8 A comprehensive participatory monitoring and evaluation system 7 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 4 74% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 7 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 11 17 established. Local-owned revenue is well managed 1 6 57% 44 Procurement Policies, procedures and controls to promote efficient and 36 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 3 3 78% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 2 3 All local government financial transactions and balances are 8 9 recorded promptly and accurately. Reliable financial and management information reports are 7 8 produced. 63% 27 Internal Audit The local government's internal audit agency is organized and 4 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 8 11 Internal audit findings are followed up adequately. 2 2 78% 18 Public Debt and Risk-based policies, procedures and controls for management of 5 8 Investment local borrowings and investments are established and implemented. 63% 8 Asset management Procedures and mechanisms for ensuring effective governance of 9 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 6 8 maintained. Asset management is linked to plans and budgets. 0 1 68% 22 External audit and External audits provide effective accountability of local government. 3 4 oversight Effective independent oversight of local government financial 3 5 management exists. 67% 9 Average 69% 256 68 8 Bireuen Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 3 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 1 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 4 6 transparency and public participation. 32% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 10 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 5 9 making processes. Budgets are pro-poor. 1 8 A comprehensive participatory monitoring and evaluation system 5 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 4 47% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 8 17 established. Local-owned revenue is well managed 3 6 36% 44 Procurement Policies, procedures and controls to promote efficient and 35 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 72% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 1 3 All local government financial transactions and balances are 2 9 recorded promptly and accurately. Reliable financial and management information reports are 7 8 produced. 41% 27 Internal Audit The local government's internal audit agency is organized and 1 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 2 2 44% 18 Public Debt and Risk-based policies, procedures and controls for management of 1 8 Investment local borrowings and investments are established and implemented. 12% 8 Asset management Procedures and mechanisms for ensuring effective governance of 2 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 5 8 maintained. Asset management is linked to plans and budgets. 1 1 36% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 3 5 management exists. 33% 9 Average 39% 256 69 9 Pidie Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 4 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 4 6 transparency and public participation. 32% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 5 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 3 8 A comprehensive participatory monitoring and evaluation system 4 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 36% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 5 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 11 17 established. Local-owned revenue is well managed 4 6 48% 44 Procurement Policies, procedures and controls to promote efficient and 36 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 72% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 1 3 All local government financial transactions and balances are 2 9 recorded promptly and accurately. Reliable financial and management information reports are 7 8 produced. 41% 27 Internal Audit The local government's internal audit agency is organized and 5 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 2 2 67% 18 Public Debt and Risk-based policies, procedures and controls for management of 0 8 Investment local borrowings and investments are established and implemented. 0% 8 Asset management Procedures and mechanisms for ensuring effective governance of 5 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 6 8 maintained. Asset management is linked to plans and budgets. 0 1 50% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 3 5 management exists. 33% 9 Average 42% 256 70 10 Aceh Tenggara Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 6 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 4 6 transparency and public participation. 48% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 9 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 6 8 A comprehensive participatory monitoring and evaluation system 3 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 49% 53 Cash management Policies, procedures and controls to promote efficient cash 4 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 3 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 4 17 established. Local-owned revenue is well managed 1 6 27% 44 Procurement Policies, procedures and controls to promote efficient and 35 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 74% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 4 9 recorded promptly and accurately. Reliable financial and management information reports are 1 8 produced. 19% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 6 11 Internal audit findings are followed up adequately. 1 2 50% 18 Public Debt and Risk-based policies, procedures and controls for management of 3 8 Investment local borrowings and investments are established and implemented. 38% 8 Asset management Procedures and mechanisms for ensuring effective governance of 3 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 3 8 maintained. Asset management is linked to plans and budgets. 1 1 32% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 1 5 management exists. 22% 9 Average 40% 256 71 11 Simeulue Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 5 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 4 6 transparency and public participation. 36% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 6 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 2 3 Budget outturns are reasonable and indicate realistic budget 8 9 making processes. Budgets are pro-poor. 7 8 A comprehensive participatory monitoring and evaluation system 1 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 51% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 10 17 established. Local-owned revenue is well managed 4 6 43% 44 Procurement Policies, procedures and controls to promote efficient and 36 49 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 76% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 6 9 recorded promptly and accurately. Reliable financial and management information reports are 8 8 produced. 52% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 6 11 Internal audit findings are followed up adequately. 2 2 56% 18 Public Debt and Risk-based policies, procedures and controls for management of 2 8 Investment local borrowings and investments are established and implemented. 25% 8 Asset management Procedures and mechanisms for ensuring effective governance of 5 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 1 1 50% 22 External audit and External audits provide effective accountability of local government. 3 4 oversight Effective independent oversight of local government financial 2 5 management exists. 56% 9 Average 49% 256 72 12 Singkil Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 7 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 44% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 5 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 7 9 making processes. Budgets are pro-poor. 8 8 A comprehensive participatory monitoring and evaluation system 3 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 51% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 5 17 established. Local-owned revenue is well managed 2 6 39% 44 Procurement Policies, procedures and controls to promote efficient and 32 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 2 3 68% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 4 9 recorded promptly and accurately. Reliable financial and management information reports are 5 8 produced. 33% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 2 2 50% 18 Public Debt and Risk-based policies, procedures and controls for management of 4 8 Investment local borrowings and investments are established and implemented. 50% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 3 8 maintained. Asset management is linked to plans and budgets. 1 1 36% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 4 5 management exists. 56% 9 Average 47% 256 73 13 Aceh Taming Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 6 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 3 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 44% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 9 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 2 9 making processes. Budgets are pro-poor. 2 8 A comprehensive participatory monitoring and evaluation system 0 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 30% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 5 17 established. Local-owned revenue is well managed 2 6 39% 44 Procurement Policies, procedures and controls to promote efficient and 28 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 58% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 5 9 recorded promptly and accurately. Reliable financial and management information reports are 4 8 produced. 37% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 1 2 44% 18 Public Debt and Risk-based policies, procedures and controls for management of 3 8 Investment local borrowings and investments are established and implemented. 38% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 2 8 maintained. Asset management is linked to plans and budgets. 1 1 27% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 1 5 management exists. 33% 9 Average 39% 256 74 14 Kota Langsa Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 9 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 56% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 12 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 3 8 A comprehensive participatory monitoring and evaluation system 5 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 4 4 55% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 5 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 7 17 established. Local-owned revenue is well managed 1 6 43% 44 Procurement Policies, procedures and controls to promote efficient and 32 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 66% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 7 9 recorded promptly and accurately. Reliable financial and management information reports are 6 8 produced. 48% 27 Internal Audit The local government's internal audit agency is organized and 3 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 6 11 Internal audit findings are followed up adequately. 2 2 61% 18 Public Debt and Risk-based policies, procedures and controls for management of 4 8 Investment local borrowings and investments are established and implemented. 50% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 0 1 36% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 1 5 management exists. 33% 9 Average 50% 256 75 15 Gayo Lues Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 6 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 36% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 11 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 5 8 A comprehensive participatory monitoring and evaluation system 3 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 51% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 5 17 established. Local-owned revenue is well managed 0 6 34% 44 Procurement Policies, procedures and controls to promote efficient and 28 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 58% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 3 7 finance functions exists. Accounting and management information systems are integrated. 3 3 All local government financial transactions and balances are 7 9 recorded promptly and accurately. Reliable financial and management information reports are 7 8 produced. 74% 27 Internal Audit The local government's internal audit agency is organized and 1 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 4 11 Internal audit findings are followed up adequately. 2 2 39% 18 Public Debt and Risk-based policies, procedures and controls for management of 2 8 Investment local borrowings and investments are established and implemented. 25% 8 Asset management Procedures and mechanisms for ensuring effective governance of 2 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 5 8 maintained. Asset management is linked to plans and budgets. 0 1 32% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 1 5 management exists. 33% 9 Average 42% 256 76 16 Aceh Barat Daya Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 4 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 1 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 1 6 transparency and public participation. 24% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 7 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 1 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 3 8 A comprehensive participatory monitoring and evaluation system 4 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 42% 53 Cash management Policies, procedures and controls to promote efficient cash 0 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 2 17 established. Local-owned revenue is well managed 0 6 14% 44 Procurement Policies, procedures and controls to promote efficient and 24 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 48% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 3 9 recorded promptly and accurately. Reliable financial and management information reports are 1 8 produced. 15% 27 Internal Audit The local government's internal audit agency is organized and 1 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 2 2 44% 18 Public Debt and Risk-based policies, procedures and controls for management of 2 8 Investment local borrowings and investments are established and implemented. 25% 8 Asset management Procedures and mechanisms for ensuring effective governance of 0 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 3 8 maintained. Asset management is linked to plans and budgets. 0 1 14% 22 External audit and External audits provide effective accountability of local government. 0 4 oversight Effective independent oversight of local government financial 1 5 management exists. 11% 9 Average 26% 256 77 17 Aceh Selatan Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 4 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 1 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 1 6 transparency and public participation. 24% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 11 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 2 3 Budget outturns are reasonable and indicate realistic budget 2 9 making processes. Budgets are pro-poor. 6 8 A comprehensive participatory monitoring and evaluation system 2 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 49% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 4 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 2 17 established. Local-owned revenue is well managed 0 6 16% 44 Procurement Policies, procedures and controls to promote efficient and 29 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 58% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 3 9 recorded promptly and accurately. Reliable financial and management information reports are 3 8 produced. 22% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 4 11 Internal audit findings are followed up adequately. 2 2 44% 18 Public Debt and Risk-based policies, procedures and controls for management of 3 8 Investment local borrowings and investments are established and implemented. 38% 8 Asset management Procedures and mechanisms for ensuring effective governance of 6 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 0 1 50% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 4 5 management exists. 56% 9 Average 40% 256 78 18 Aceh Tengah Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 4 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 32% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 8 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 3 9 making processes. Budgets are pro-poor. 5 8 A comprehensive participatory monitoring and evaluation system 2 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 40% 53 Cash management Policies, procedures and controls to promote efficient cash 1 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 6 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 3 17 established. Local-owned revenue is well managed 0 6 23% 44 Procurement Policies, procedures and controls to promote efficient and 27 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 1 3 56% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 5 9 recorded promptly and accurately. Reliable financial and management information reports are 3 8 produced. 30% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 3 11 Internal audit findings are followed up adequately. 1 2 33% 18 Public Debt and Risk-based policies, procedures and controls for management of 1 8 Investment local borrowings and investments are established and implemented. 13% 8 Asset management Procedures and mechanisms for ensuring effective governance of 2 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 2 8 maintained. Asset management is linked to plans and budgets. 1 1 27% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 2 5 management exists. 44% 9 Average 33% 256 79 19 Bener Meriah Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 2 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 1 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 20% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 5 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 1 9 making processes. Budgets are pro-poor. 4 8 A comprehensive participatory monitoring and evaluation system 4 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 30% 53 Cash management Policies, procedures and controls to promote efficient cash 2 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 3 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 3 17 established. Local-owned revenue is well managed 0 6 18% 44 Procurement Policies, procedures and controls to promote efficient and 19 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 38% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 0 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 3 9 recorded promptly and accurately. Reliable financial and management information reports are 1 8 produced. 15% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 3 11 Internal audit findings are followed up adequately. 1 2 33% 18 Public Debt and Risk-based policies, procedures and controls for management of 1 8 Investment local borrowings and investments are established and implemented. 13% 8 Asset management Procedures and mechanisms for ensuring effective governance of 3 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 2 8 maintained. Asset management is linked to plans and budgets. 1 1 27% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 3 5 management exists. 33% 9 Average 25% 256 80 20 Kota Sabang Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 4 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 36% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 4 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 4 9 making processes. Budgets are pro-poor. 3 8 A comprehensive participatory monitoring and evaluation system 6 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 1 4 34% 53 Cash management Policies, procedures and controls to promote efficient cash 2 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 8 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 7 17 established. Local-owned revenue is well managed 1 6 41% 44 Procurement Policies, procedures and controls to promote efficient and 27 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 54% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 3 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 7 9 recorded promptly and accurately. Reliable financial and management information reports are 6 8 produced. 59% 27 Internal Audit The local government's internal audit agency is organized and 3 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 4 11 Internal audit findings are followed up adequately. 2 2 50% 18 Public Debt and Risk-based policies, procedures and controls for management of 0 8 Investment local borrowings and investments are established and implemented. 0% 8 Asset management Procedures and mechanisms for ensuring effective governance of 4 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 3 8 maintained. Asset management is linked to plans and budgets. 1 1 41% 22 External audit and External audits provide effective accountability of local government. 2 4 oversight Effective independent oversight of local government financial 3 5 management exists. 56% 9 Average 41% 256 81 21 Kota Lhokseumawe Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 3 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 0 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 3 6 transparency and public participation. 24% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 5 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 1 9 making processes. Budgets are pro-poor. 4 8 A comprehensive participatory monitoring and evaluation system 5 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 2 4 33% 53 Cash management Policies, procedures and controls to promote efficient cash 5 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 5 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 6 17 established. Local-owned revenue is well managed 0 6 36% 44 Procurement Policies, procedures and controls to promote efficient and 16 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 32% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 1 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 3 9 recorded promptly and accurately. Reliable financial and management information reports are 5 8 produced. 33% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 5 11 Internal audit findings are followed up adequately. 2 2 50% 18 Public Debt and Risk-based policies, procedures and controls for management of 0 8 Investment local borrowings and investments are established and implemented. 0% 8 Asset management Procedures and mechanisms for ensuring effective governance of 0 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 0 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 0 1 18% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 2 5 management exists. 33% 9 Average 29% 256 82 22 Aceh Provincial Government Strategic area Outcomes Indicators No. of achieved indicators Local regulatory A comprehensive local regulatory framework required by national 5 12 framework legislation on local financial management exists. The local regulatory framework provides for an effective law 2 7 enforcement and organizational structure. The local regulatory framework includes measures to increase 2 6 transparency and public participation. 36% 25 Planning and Budgeting A consistent link between bottom-up planning processes, local 3 17 development plans, sector plans and the budget exists. Budgets are based on a medium-term time horizon. 0 3 Budget outturns are reasonable and indicate realistic budget 5 9 making processes. Budgets are pro-poor. 5 8 A comprehensive participatory monitoring and evaluation system 7 9 for planning and budgeting processes is established. Expenditure control is used to ensure budget efficiency 3 4 46% 53 Cash management Policies, procedures and controls to promote efficient cash 6 10 management are in place. Cash receipts cash payments and temporary cash surpluses are 5 11 managed and controlled effectively. An efficient system for billing and collecting local revenues is 7 17 established. Local-owned revenue is well managed 0 6 41% 44 Procurement Policies, procedures and controls to promote efficient and 26 47 competitive procurement of goods and services are established and implemented. Complaints handling system is operating. 0 3 52% 50 Accounting and Reporting Adequate human and institutional capacity for accounting and 2 7 finance functions exists. Accounting and management information systems are integrated. 0 3 All local government financial transactions and balances are 7 9 recorded promptly and accurately. Reliable financial and management information reports are 6 8 produced. 56% 27 Internal Audit The local government's internal audit agency is organized and 2 5 empowered to operate effectively. Internal audits standards and procedures applied are acceptable 7 11 Internal audit findings are followed up adequately. 2 2 61% 18 Public Debt and Risk-based policies, procedures and controls for management of 0 8 Investment local borrowings and investments are established and implemented. 0% 8 Asset management Procedures and mechanisms for ensuring effective governance of 3 10 local enterprises are established. Policies, procedures and controls for acquisition of new assets and 1 3 effective management of existing long-term physical assets are established and implemented. Supporting asset management information base is established and 4 8 maintained. Asset management is linked to plans and budgets. 1 1 41% 22 External audit and External audits provide effective accountability of local government. 1 4 oversight Effective independent oversight of local government financial 1 5 management exists. 56% 9 Average 43% 256 83 Annex 4: Methodology The outcomes in the PFM framework are linked to specific local government departments. A meeting is first held with the head of the local government - Bupati in a district governments and Walikota in a city administration. In some instances, the government head was represented by the SekDa (Sekretaris Daerah) or the head of the regional work plan (SKPD). The purpose is to explain the aims of the survey and hold a discussion with the participants about financial management in the local government. It is emphasized that the aim of the survey is to identify relative strengths and weaknesses in the local government's financial management capacity. Participants are informed that the survey covers every local government in Aceh and the results will be made available. Whilst no commitments are made concerning capacity building interventions, it is emphasized that it is in the best interests of the respondents to answer accurately and truthfully. The research teams are divided into smaller groups, usually of two people each and tasks are assigned to each group. The table below provides a guideline as to which strategic areas and outcomes are relevant to which department. The teams should, if deemed necessary, crosscheck the answers with officials from other departments. All relevant documentation is checked usually at the time of the interview or later if immediately unavailable. This not only confirms (or refutes) the accuracy of the response but also provides an additional incentive to provide accurate responses. Yes/no responses are entered directly into the PFM scoring framework, which automatically calculates all the scores. Space is provided for supporting comments. Each research team leader is required to provide a written report on each local government surveyed. The aim is to present a context for the PFM scores by providing qualitative analysis to support the scores. A format is provided to the research team leaders. In the case of unexpectedly high or low scoring, research teams are encouraged to re-check responses and, if appropriate, re-interview respondents. As a result, the scores for two local governments were revised. 84 The PFM Framework and Relevant Local Government Departments STRATEGIC AREA/OUTCOME RELEVANT DEPARTMENT Strategic Area 1: Local Regulatory Framework Outcome No. 1 Legal Department, Bappeda, Finance Department Outcome No. 2 Bappeda, Finance Department Outcome No.3 Bappeda, Finance Department Strategic Area 2: Planning and Budgeting Outcome No. 1 Bappeda, Finance Department Outcome No. 2 Bappeda, Finance Department Outcome No.3 Bappeda, Finance Department Outcome No.4 Bappeda, Finance Department Outcome No.5 Bappeda, Finance Department, Bawasda (indicator 4) Outcome No.6 Bappeda, Finance Department Strategic Area 3: Cash Management Outcome No. 1 Finance Department, Bawasda (Indicator 10) Outcome No. 2 Finance Department, Dispenda Outcome No.3 Finance Department, Bawasda, Dispenda Outcome No.4 Finance Department, Bawasda, Dispenda Strategic Area 4: Procurement Outcome No. 1 BPKP, General Works Department, Legal Department, Bawasda, Finance Department Outcome No. 2 Legislative Body, BPKP Strategic Area 5: Accounting and Reporting Outcome No. 1 Finance Department Outcome No. 2 Finance Department Outcome No.3 Finance Department Outcome No.4 Finance Department Strategic Area 6: Internal Audit Outcome No. 1 Bawasda Outcome No. 2 Bawasda Outcome No.3 Bawasda Strategic Area 7: Debt and Investment Outcome No. 1 Finance Department Strategic Area 8: Asset Management Outcome No. 1 Finance Department, Bawasda (indicator 5), Setda and/or Director BUMD Outcome No.2 Finance Department Outcome No. 3 Finance Department Outcome No. 4 Finance Department Strategic Area 9: Oversight and External Audit Outcome No. 1 Finance Department, Legislative Assembly member Outcome No.2 Finance Department, Legislative Assembly member, Setda 85 Annex 5: Researchers and Universities The Public Financial Management survey was carried out in three stages between May and November 2006. Each research team was comprised of four or five researchers from the following Indonesian universities and NGOs. LGSP provided team leaders for the first survey round in five local governments. Institution Researchers Hasanudin University, Makassar Drs. H. Muhammad Toaha, Drs. Harryanto, M.Com. MBA Gagaring Pagalung, SE., Yansor Djaya MS., Akt.Phd.Cand. Syahrir, SE, M. Si, Ak Drs. Nasruddin, MM M. Natsir Kadir, Drs. M. Si., Kastumuni Harto Akt. Andalas University, Padang Drs. H.Masrizal, MSoc, Sc Rahmat Febrianto,SE, Msi, Akt DR.H. Suhairi, SE, Msi, Akt DR.H. Hefrizal Handra, MSoc, Sc Suhanda, SE, Msi, Akt Fajri Muharja, SE, Msi Rafdinal, SE, Msi, Akt DR. H. Sofyardi, SE, MA University of North Sumatra, M. Utama Nasution, SE, Dr. Erlina Roesli, MSi, Medan MM, Ak. Ak Drs. Rasdianto, MSi, Ak Syamsul Bahri TRB Drs. Arifin Lubis, MM, Ak. UNSYIAH University, Banda Aceh Prof. Djamaluddin Bismi Khalidin Muhammad Saleh Ahmad IAIN AR-Raniry Banda Aceh Bismi Khalidin Israk Ahmadsyah TARI Research Institute, Banda Nashrillah Anis, SE, MM Zahrial, SE Aceh Miftachhuddin Cut Adek, SE, M.Si USAID-LGSP Arham Rauf Farman Izhar Utoro Sindhubilowo Sigit Purwanto 86 Annex 6: PFM outcomes in all 21 Local Governments in Aceh 87 88